Management Advisory Report:  Project Management Techniques Would Help in Managing Risks For the Increased Employee Plan Determination Letter Workload

 

May 2002

 

Reference Number:  2002-10-104

 

 

 

This report has cleared the Treasury Inspector General for Tax Administration disclosure review process and information determined to be restricted from public release has been redacted from this document.

 

May 30, 2002

 

 

 

MEMORANDUM FOR COMMISSIONER, TAX EXEMPT AND GOVERNMENT ENTITIES DIVISION

 

FROM:     Pamela J. Gardiner /s/ Pamela J. Gardiner

                 Deputy Inspector General for Audit

 

SUBJECT:    Final Management Advisory Report:  Project Management Techniques Would Help in Managing Risks For the Increased Employee Plan Determination Letter Workload (Audit # 200110050)

 

This report presents the results of our review of the Tax Exempt and Government Entities (TE/GE) Division’s strategy for processing an anticipated higher number of employee plan determination letter applications.  The overall objective of this review was to determine if potential risks to the implementation of the employee plans determination letter strategy are being effectively addressed by the TE/GE Division. 

In summary, we found that the TE/GE Division designed a multifaceted strategy to address the challenge of continuing to provide top-quality service to all employee plan customers during the expected peak in the determination letter application workload.  The strategy reflects a high level of commitment to minimizing any detrimental impact on customer satisfaction or customer burden that might be caused if the increased number of applications causes delays in processing determination requests.  Timely responses are important.  If the terms of a benefit plan are incomplete or incorrect, a prompt determination from the Internal Revenue Service (IRS) will enable the employer to make the necessary corrections as quickly as possible. 

Although TE/GE management developed a strategy to prepare for the peak determination letter workload, we believe project management techniques should be used to effectively implement the determination letter strategy.  The TE/GE Division’s strategy did not include a structured project management approach to coordinate, monitor, or report on the actions in process by all the various functions involved with implementing the strategy.  Instead, TE/GE management used conference calls and status meetings to discuss the actions needed to prepare for the peak receipt period.  This made it difficult to know whether the TE/GE Division would be ready to handle the increased workload when the peak period began, as well as to identify new risks as the strategy unfolds.  A structured approach would help all levels of TE/GE management review what issues exist and assess whether associated risks have been addressed to their satisfaction.

Management’s Response:  TE/GE management agreed with our recommendation and appointed a manager to assume program responsibility and apply project management techniques for the increase in determination letter workload.  Management’s complete response to the draft report is included as Appendix IV.

Copies of this report are also being sent to the IRS managers who are affected by the report recommendation.  Please contact me at (202) 622-6510 if you have questions or Daniel R. Devlin, Assistant Inspector General for Audit (Headquarters Operations and Exempt Organizations Programs), at (202) 622-8500.

 

 

Table of Contents

Background

A Multifaceted Strategy Has Been Designed to Address the Expected Peak in the Employee Plan Determination Letter Workload

Project Management Techniques Should Be Used to Effectively Implement the Determination Letter Strategy

Recommendation 1:

Appendix I – Detailed Objective, Scope, and Methodology

Appendix II – Major Contributors to This Report

Appendix III – Report Distribution List

Appendix IV – Management’s Response to the Draft Report

 

Background

Employer-sponsored employee benefit plans must comply with numerous laws and regulations in order to qualify for favorable tax treatment of the plan’s assets.  Examples of favorable tax treatment for a plan that meets the qualification requirements include:  the assets and income of the plan are tax-exempt, contributions to and expenses incurred by the plan are deductible, and participants are not taxed on their benefits until distributions are received from the plan. 

Many employers want to know if, in the opinion of the Internal Revenue Service (IRS), the terms of their plans satisfy the qualification requirements.  The IRS provides a way for employers to get such an assurance by means of the determination letter program.  In the determination letter program, the IRS evaluates the employer’s benefit plan to determine its compliance with the requirements.  If the IRS identifies unacceptable features, the employer is given an opportunity to make appropriate modifications to the plan.  When the format of a plan satisfies the applicable requirements, the IRS issues a favorable determination letter.  While employers are not required to request a determination letter, a favorable letter gives the employer a reliance that the plan is qualified and that, as a result, it is entitled to favorable tax treatment as long as the plan is operated under the terms on which the letter was issued.

A favorable determination letter is limited in scope and may also have a limited useful life.  In general, the IRS issues a determination letter based on the law in effect at the time the application for a determination was received.  If there is a subsequent change in a statute, regulation, or revenue ruling applicable to the plan, the plan must be amended to comply with the new requirements and to maintain its qualified status.  As a result, after modifying the plan, the employer would need to again ask for a determination letter to have reliance that the plan was properly redesigned.

The IRS allows plan sponsors time to incorporate tax law changes without any penalty or sanction.  This is called the remedial amendment period.  The end of the remedial period becomes a deadline for the timely filing of a determination letter application that relates to the changes in requirements. 

Varying remedial periods can be set for different laws, types of amendments, or types of applications involved.  The IRS can, and has, extended the remedial amendment period for certain statutes and consolidated several laws’ provisions into one remedial period. 

The ending of the remedial period for one group of tax law changes, which the IRS refers to as GUST, was scheduled for December 31, 2001.  Based on the likelihood that employers would ask for a determination letter on their revised benefit plans, the IRS estimated that the number of determination letter applications may quadruple during Fiscal Years (FY) 2002 and 2003 as compared to normal receipt levels.  The IRS has had other peak periods of receipts around 1995, 1986, and 1978.

On November 14, 2001, the IRS announced that as a result of the September 11, 2001, terrorist attack on the United States, the deadline for timely filing for many determination letter applicants (i.e., the beginning of the peak period) was extended.  Depending on the type of employer plan, the end of the GUST remedial period was extended to February 28, 2002, or to alternate dates spread across Calendar Years 2002 and 2003 on a plan-by-plan basis.  Based on these revised dates and the fact that determination applications are voluntary, the actual number and timing of applications that will be received by the IRS is not certain.

We contacted personnel in the IRS Tax Exempt and Government Entities (TE/GE) Division and other IRS divisions in Cincinnati, Ohio, and Washington, D.C., between August 2001 and March 2002.  The review was conducted in accordance with the President’s Council on Integrity and Efficiency’s Quality Standards for Inspections.  Detailed information on our objective, scope, and methodology is presented in Appendix I.  Major contributors to the report are listed in Appendix II.

A Multifaceted Strategy Has Been Designed to Address the Expected Peak in the Employee Plan Determination Letter Workload

The TE/GE Division designed a multifaceted strategy to address the challenge of continuing to provide top-quality service to all employee plan customers during the expected peak in the determination letter application workload.  This is prominently shown in the TE/GE Division’s FY 2002-2003 Strategic Assessment, Strategic Plan, and Program Plan; as well as the FY 2001 Business Performance Review.  General management techniques, such as defining operational priorities and improvement projects, are used at this level.  Major components of the strategy include:

·        Adding employees and other resources to the determination letter program to help process the higher number of applications.

·        Using various customer education and outreach strategies to help employers understand and comply with the application process.

·        Identifying improvement projects to address information system issues that have an impact on the determination letter program. 

The TE/GE Division’s strategy reflects a high level of commitment to minimizing any detrimental impact on customer satisfaction or customer burden that might be caused if the increased number of applications causes delays in processing determination requests.  For FY 2002, the TE/GE Division has given priority to the strategy within its Employee Plans (EP) function.  For example, management is shifting a significant part of the staff resources from the EP examination program to the EP determination program.  These agents will be trained to review and process determination applications.  Also, additional sites will be set up to screen the incoming applications.  Normally, all determination letter applications are screened in one centralized location in order to separate those that could be given a favorable letter based on the merit of the documents provided with the application and those that need further review by an EP revenue agent.  In anticipation of the increase in applications, the strategy includes establishing up to six additional screening sites throughout the country in order to minimize any backlogs at the screening level.

This commitment is commensurate with the TE/GE Division’s belief that the determination letter program is the IRS’ key link to the employee benefits plan community.  The IRS, through the determination letter program, informs employers if their plan formats comply with the current laws, essentially protecting millions of participating employees from unintended tax consequences.

Project Management Techniques Should Be Used to Effectively Implement the Determination Letter Strategy

Although TE/GE management developed a strategy to prepare for the peak determination letter workload, additional efforts are needed to ensure that potentially critical issues are prominently in the view of TE/GE management.  If issues are not resolved as they occur, there is a risk that events could hamper the TE/GE Division’s ability to effectively implement the overall strategy, which focuses on timely issuing determination letters and maintaining good customer service.  If determination letters are delayed, it could result in increased burden on employers that are waiting for a determination on their employee plans.

The TE/GE Division’s strategy did not include a structured project management approach to coordinate, monitor, or report on the actions in process by all the various functions involved with implementing the strategy.  Instead, TE/GE management used conference calls and status meetings to discuss the actions needed to prepare for the peak receipt period.  However, because there were no overall lists of completed tasks, outstanding items, or risks identified, TE/GE management did not have a tool that tracked the readiness of all aspects of the strategy.  This made it difficult to know whether the TE/GE Division would be ready to handle the increased workload when the peak period began, as well as to identify new risks as the strategy unfolds.

To illustrate the effects of not using a structured management approach, we cite three examples where risks had not been timely or completely resolved prior to December 31, 2001, the original date for the beginning of the peak period.   

Formal notification of process changes to the employees’ union

As the application screening and assignment strategy was being developed by the TE/GE Division, a labor relations specialist advised that the impact of modifying some revenue agents’ work assignments warranted a formal notification to the IRS employees’ union under the labor/management bargaining provisions.  TE/GE management initially considered this and had preliminary contacts with union representatives regarding the strategy and the change in work assignments.  In September 2001, they decided it was not necessary to pursue the formal concurrence of the employees’ union.  However, subsequent to this decision, as the peak receipt period neared, other TE/GE officials indicated they thought a formal notification to the employees’ union was still being planned.  At the time of our review, it was not clear if TE/GE management had completely resolved whether a formal notification was warranted.  Processing delays could occur if formal negotiations become necessary during the peak period.

Capacity of the automated determination letter processing system

The TE/GE Division’s FY 2002 Strategic Plan indicated that a redesign of the current automated determination letter processing system was necessary to avoid downtime and delays because the system was stretched beyond its capacity.  The TE/GE Division’s strategy for processing the increased volume of applications may aggravate this condition since many employees may be shifted to the determination program, which will increase the number of potential system users.  For example, one of the system constraints was a limit of 250 simultaneously logged-on users.  System administrators told us that the system was already approaching the 250-user limit before the peak period began and that approximately 245 new user profiles were added between July 1, 2001, and January 16, 2002.  The TE/GE Division indicated that a contingency plan would be to stagger the users’ access to the system, if necessary.

As the peak receipt period neared, it was not clear if TE/GE management had completely resolved whether system issues could limit the effectiveness of the workload distribution strategy.  If the new users attempt to log-on to the system along with the regular users, the system limit may be exceeded and the TE/GE Division will have to address system problems sooner than planned.  Processing delays could occur if all the anticipated users cannot efficiently access the system or if the responsiveness of system access is significantly degraded because of an increase in users.

Resources for the initial processing of applications

The TE/GE Division’s Business Performance Review indicated that the higher volumes of applications will require additional resources to maintain the timeliness of the IRS’ initial clerical processing of determination letter applications, which is done by the Small Business/Self-Employed (SB/SE) Division Submission Processing Center staff.  The TE/GE Division and the SB/SE Division estimated that 50 additional staff years above the historical base of 30 staff years would be required for FY 2002.  As the peak receipt period neared, the SB/SE Division was still in the process of recruiting and hiring additional employees for the higher volume of determination work expected and had not yet received additional computer terminals that had been ordered.  The TE/GE Division indicated that, historically, the processing center has been able to take steps to handle resource issues, when necessary.

It was not clear if TE/GE management had completely resolved whether the SB/SE Division’s level of readiness would create bottlenecks if large volumes were actually received at the deadline date and the hiring and training had not been completed.  The IRS subsequently extended the date for the end of the remedial period, which also gave the IRS additional time to hire staff and obtain equipment.

Project management techniques would help

One of the standards for effective internal control in government is that management should identify and analyze risks associated with achieving their objectives.  Methods for doing this vary, so management must select an appropriate way to manage risks.

We believe that project management techniques would have helped all levels of TE/GE management review what issues exist and assess if associated risks have been addressed to their satisfaction.  A structured approach would also help highlight issues for management attention throughout the duration of the strategy.  Project management is defining, planning, scheduling, and controlling the tasks that must be completed to accomplish project goals.  Project management techniques can help organize the details of a project by listing tasks or action items to be accomplished, setting schedule or milestone dates, having regular progress reviews, and listing any changes that need to be made or issues that need action.  Using these tools normally requires that a project manager or team leader be designated.  While TE/GE management used some of these techniques, they did not formally designate a project manager to ensure that project management techniques are applied throughout the implementation of the strategy.

The TE/GE Division acknowledges that peak receipt periods make it exceptionally difficult to maintain good customer service.  Employers suffer additional burdens as the time frame for receiving their determination letters lengthens.  Timely responses are important.  If the changes to the benefit plans as a result of the GUST are incomplete or incorrect, a prompt determination from the IRS will enable the employer to make the necessary corrections as quickly as possible.  This has downstream impacts on the IRS as well, because it must dedicate more resources to respond to customers inquiring about the status of their determination application.

Individuals, organizations, and the public at large rely on the IRS to ensure that employee benefit plans follow the complex tax laws and guidance that regulate their operations.  The IRS’ effectiveness in providing prompt customer service in the determination letter area helps in maintaining public confidence and fairness in tax administration.   

Recommendation

1.      The Commissioner, TE/GE Division, should designate a manager to assume the responsibility of using appropriate project management techniques as soon as possible and for the duration of the EP determination letter strategy (through FYs 2002 and 2003, or until the volume of applications returns to normal levels).

Management’s Response:  The Director, EP function, appointed a manager to assume program responsibility and apply project management techniques for the increase in the determination letter workload.

 

Appendix I

 

Detailed Objective, Scope, and Methodology

 

The overall objective of this review was to determine if potential risks to the implementation of the employee plans determination letter strategy are being effectively addressed by the Tax Exempt and Government Entities (TE/GE) Division.  To accomplish this objective, we: 

I.                    Determined if there were unresolved readiness issues pertaining to the TE/GE Division’s Employee Plans (EP) determination letter strategy.

A.     Reviewed the draft versions of the TE/GE Division’s Fiscal Year (FY) 2002-2003 Strategic Assessment, FY 2002-2003 Strategy and Program Plans, FY 2002 EP Work Plan, and Business Performance Review.

B.     Reviewed other available documents that communicated the determination letter strategy, such as management slide-show presentations, memoranda, TE/GE Division newsletters, and Internal Revenue Service (IRS) notices and announcements.

C.     Interviewed TE/GE Division personnel responsible for selected segments of the strategy to gauge the level of readiness to implement the strategy.  As applicable, interviewed personnel of other IRS functions where activities were relevant to the EP strategy (Information Technology Services, Small Business/Self-Employed Submission Processing, and Statistics of Income).

D.     Evaluated the status of major segments in the strategy and identified incomplete tasks or unresolved problems that appeared to have the potential to adversely impact the strategy if not timely addressed.

II.                 Determined if management oversight appeared effective in identifying significant issues and ensuring that action items were monitored.

A.     Interviewed TE/GE management personnel to determine if an overall issue owner or project leader had been designated to coordinate the strategy’s implementation or if there were written implementation plans that included all the functions that have a role in processing the determination letter applications.

B.     Discussed unresolved issues and the related potential risks with EP management to determine their roles in providing oversight to the strategy.

 

Appendix II

 

Major Contributors to This Report

 

Daniel R. Devlin, Assistant Inspector General for Audit (Headquarters Operations and Exempt Organizations Programs)

Joseph W. Edwards, Director

Nancy A. Nakamura, Director

Ronald F. Koperniak, Audit Manager

Timothy A. Chriest, Senior Auditor

Janice A. Murphy, Senior Auditor

Joseph P. Snyder, Senior Auditor

 

Appendix III

 

Report Distribution List

 

Commissioner  N:C

Deputy Commissioner, Tax Exempt and Government Entities Division  T

Director, Employee Plans, Tax Exempt and Government Entities Division  T:EP

Director, Rulings and Agreements, Tax Exempt and Government Entities Division  T:EP:RA

Manager, Employee Plans Determinations, Tax Exempt and Government Entities Division  T:EP:RA:D

Chief Counsel  CC

National Taxpayer Advocate  TA

Director, Legislative Affairs  CL:LA

Director, Office of Program Evaluation and Risk Analysis  N:ADC:R:O

Office of Management Controls  N:CFO:F:M

Audit Liaisons:

Commissioner, Small Business/Self-Employed Division  S:COM

Director, Communications and Liaison, Tax Exempt and Government Entities

Division  T:CL

 

Appendix IV

 

Management’s Response to the Draft Report

 

The response was removed due to its size.  To see the complete response, please go to the Adobe PDF version of the report on the TIGTA Public Web Page.