The Hardware Refreshment Program Is Generally Effective, But Improvements Can Be Made

 

September 2002

 

Reference Number:  2002-20-160

 

 

This report has cleared the Treasury Inspector General for Tax Administration disclosure review process and information determined to be restricted from public release has been redacted from this document.

 

September 11, 2002

 

 

MEMORANDUM FOR DEPUTY COMMISSIONER FOR MODERNIZATION &
CHIEF INFORMATION OFFICER

 

FROM:     Pamela J. Gardiner /s/ Pamela J. Gardiner

                 Acting Inspector General

 

SUBJECT:     Final Audit Report - The Hardware Refreshment Program Is Generally Effective, But Improvements Can Be Made (Audit # 200220040)

 

This report presents the results of our review of the effectiveness of the Hardware Refreshment Program (HRP).

In summary, by the end of Fiscal Year (FY) 2003, the Internal Revenue Service (IRS) expects to have replaced its aging inventory of 150,000 personal computers with approximately 107,000 new (refreshed) personal computers.  The Hardware Refreshment Program Office (HRPO) of the End User Equipment and Services Division is responsible for coordinating and overseeing the planning and implementation of the HRP. 

In FY 2001, the IRS allocated approximately $97 million to replace 63,139 personal computers.  On May 14, 2001, the IRS held a reverse auction to purchase the replacement computers with installation beginning in FY 2002.  The IRS reported that the reverse auction resulted in government savings of 49 percent.  The new computers were targeted to replace existing low-end computers with processor speeds less than 400 megahertz.  As of June 6, 2002, the IRS had replaced 36,423 (25,875 desktops and 10,548 laptops) of the 63,139 personal computers and plans to replace the remaining computers before the end of FY 2002.  For FYs 2002 and 2003, the IRS budgeted $86.4 million to purchase and install an additional 45,560 computers by the end of FY 2003.

Overall, the HRPO has done an effective job controlling the hardware replacement process.  The HRPO successfully implemented several program management activities such as preparing key program management documents, educating employees, and providing training.  However, the HRPO could improve the hardware replacement process by identifying, documenting, and communicating lessons learned.

For example, at one of the sites we visited that began the rollout of its new computers in February 2002, several employees in two business units were negatively affected by the computer replacement.  The new computers significantly reduced the employees’ Internet research capabilities, thus affecting their ability to effectively complete required duties.  A similar situation was reported to IRS executives in December 2001, but it was not communicated to the site before computer replacement occurred.

The Deputy Commissioner for Modernization & Chief Information Officer should ensure post-installation conference calls are held to identify lessons learned during site installations and that lessons learned are formally documented and effectively communicated to future computer replacement sites.

Management’s Response:  IRS management agreed to the recommendations presented.  The HRPO will ensure offices hold post-installation conference calls, and it will update the Lessons Learned document with issues that may affect future site installations.  The Lessons Learned document will be available on the Hardware Refreshment web page to all Modernization, Information Technology, and Security Services employees and customers for information.

Management’s complete response to the draft report is included as Appendix IV.

Copies of this report are also being sent to the IRS managers who are affected by the report recommendations.  Please contact me at (202) 622-6510 if you have questions or Scott E. Wilson, Assistant Inspector General for Audit (Information Systems Programs), at (202) 622-8510.

 

Table of Contents

Background

The Hardware Refreshment Program Office Successfully Implemented Several Program Management Activities

Identifying, Documenting, and Communicating Lessons Learned Would Improve the Hardware Replacement Process

Recommendations 1 and 2:

Appendix I – Detailed Objective, Scope, and Methodology

Appendix II – Major Contributors to This Report

Appendix III – Report Distribution List

Appendix IV – Management’s Response to the Draft Report

 

Background

One of the Internal Revenue Service’s (IRS) major strategies contained in the IRS Strategic Plan Fiscal Years (FY) 2000 – 2005 is to provide high quality, efficient, and responsive information services to internal customers.  As part of this strategy, the Modernization, Information Technology, and Security Services (MITS Services) FY 2002-2003 Program Plan established that an infrastructure be provided that is sufficiently flexible to adapt to evolving business needs and can be efficiently managed, specifically establishing enterprise-wide technology refreshment (i.e., routine replacement of low-end computer workstations) as an operational priority.

The Hardware Refreshment Program Office (HRPO) of the End User Equipment and Services (EUES) Division is responsible for coordinating and overseeing the planning and implementation of the Hardware Refreshment Program (HRP).  The HRP involves the IRS-wide initiative to routinely replace aging personal computers (desktop and laptop computers) with state of the market equipment on a continuing refreshment cycle (currently, 3 years) while reducing the personal computer inventory in the IRS to a ratio of 1 computer per employee.  By the end of FY 2003, the IRS expects to have replaced its aging inventory of 150,000 personal computers with approximately 107,000 new (refreshed) personal computers.

In FY 2001, the IRS allocated approximately $97 million to replace 63,139 personal computers.  On May 14, 2001, the IRS held a reverse auction to purchase the replacement computers with installation beginning in FY 2002.  The IRS reported that the reverse auction resulted in government savings of 49 percent.  The new computers were targeted to replace existing low-end computers with processor speeds less than 400 megahertz.  As of June 6, 2002, the IRS had replaced 36,423 (25,875 desktops and 10,548 laptops) of the 63,139 personal computers and plans to replace the remaining computers before the end of FY 2002.  For FYs 2002 and 2003, the IRS budgeted $86.4 million to purchase and install an additional 45,560 computers by the end of FY 2003. 

Audit work was conducted in the Information Technology Services (ITS) National Headquarters, the Memphis IRS Campus, the Tennessee Computing Center, and the Denver and Indianapolis Area Offices during the period February through June 2002.  This audit was initiated at the request of the Deputy Commissioner for Modernization & Chief Information Officer and was conducted in accordance with Government Auditing Standards.  Detailed information on our audit objective, scope, and methodology is presented in Appendix I.  Major contributors to the report are listed in Appendix II.

The Hardware Refreshment Program Office Successfully Implemented Several Program Management Activities

The Office of Management and Budget (OMB) Circular A-130, Management of Federal Information Resources, requires the head of each federal agency to effectively and efficiently manage agency information and information technology and to develop policies and procedures that provide for timely acquisition of required information technology.

Overall, the HRPO has done an effective job controlling the hardware replacement process.  Program management activities successfully implemented by the HRPO included developing key program management documents, effectively educating affected employees about the HRP, and ensuring that any requested training was provided.  The local ITS support personnel were also very supportive of the replacement effort and assisted the HRPO by coordinating site rollout activities and validating the personal computer inventory.  As a result, the users at sites visited during the audit were generally satisfied with the overall hardware replacement process.

Key program management documents

The HRPO developed a comprehensive Hardware Refreshment Program Management Plan to provide structure in planning, organizing, directing, and controlling hardware replacement activities.  Although not formally approved, this Plan provides extensive guidance regarding the implementation of a continuous hardware replacement process.  The Plan also identifies risks to be considered throughout the replacement process and details the roles and responsibilities of the EUES Division, HRPO, contractor, and local ITS support personnel at the individual IRS sites.

The HRPO also developed a Work Breakdown Structure to identify the major tasks to be performed and to track the status and completion of those tasks.  A hardware replacement schedule was also prepared to track and monitor replacement activities at each site.  The schedule identifies the computer replacement dates by site and the quantity of desktop and laptop computers to be replaced.  The schedule is updated weekly based on information obtained from the installation sites during hardware replacement status meetings and conference calls.  For example, the HRPO conducted regular coordination meetings with ITS support and business unit personnel at each site to discuss replacement activities prior to delivery of replacement hardware.  In addition, the HRPO conducted daily conference calls with ITS support personnel at each site to confirm the schedule, workspace readiness, and delivery of equipment.

The HRPO also prepared a cost/benefit analysis for the replacement process.  The analysis information presented to the OMB compared hardware refreshment scenarios of 3, 4, and 5 years.  Based on industry “best practices” and the results of the cost/benefit analysis, IRS management selected the 3-year computer replacement scenario.  Lengthening the replacement process to 4 or 5 years was shown to have significant cost impacts.  For example, the additional tangible costs for repairs and upgrades were projected to exceed $74 million under the 4-year scenario and $100 million under the 5-year scenario.  Additional impacts of lengthening the replacement process, which are difficult to quantify, included a delay in implementing improvement projects across the IRS and an increase in user downtime.

The HRPO also documented planned benefits, which included providing current technology and standardized software applications IRS-wide and minimizing costs through bulk hardware purchases.

Employee education

The HRPO developed and implemented an extensive Communications Plan that provided for the development and distribution of various internal communication vehicles to educate IRS employees about the HRP.  The communication vehicles include web sites, newsletters, brochures, and posters.  The local ITS support personnel also communicated the HRP message to the appropriate site management to facilitate educating site employees.  At the sites we visited, managers held group meetings to provide HRP information to employees.  As a result, employees generally stated that the information they received regarding local HRP activities was adequate and timely communicated.

Training

At the four sites we visited, the desktop computers were replaced with no new functionality or additional applications; therefore, minimal or no training was required by the personnel receiving the new computers.  The laptop computers contained new features and the HRPO designated the local ITS support personnel as responsible for providing informal training on the hardware when requested by employees.  This training was accomplished through a combination of classroom training, group sessions, and/or one-on-one assistance.  Overall, users were satisfied with the training or assistance they received on their new computers.

Identifying, Documenting, and Communicating Lessons Learned Would Improve the Hardware Replacement Process

The OMB Circular A-130 requires each federal agency to document lessons learned to ensure that agencies manage information technology in an effective and efficient manner.  While several program management activities were implemented to control the hardware replacement process, the HRPO did not identify and formally document and communicate lessons learned to ensure the most efficient and effective use of resources.

HRPO management indicated that, at the time of installation, they conduct daily telephone calls to discuss the status of computer replacement at the sites.  However, planned post-installation conference calls were not held to identify and track issues and ensure that lessons learned were documented and communicated to offices scheduled to go through the hardware replacement process.

At one of the sites we visited that began the rollout of its new computers in February 2002, several employees in two business units were negatively affected by the computer replacement.  The new computers significantly reduced the employees’ Internet research capabilities due to the configuration of the Microsoft Internet Explorer software, thus affecting their ability to effectively complete required duties.  Representatives of 1 of the business units stated that as many as 300 of the business unit’s users nationwide could have been affected by the Internet-related access limitations.  Due to the computer replacement limiting the employees’ research capabilities, the employees resorted to using their home computers to conduct their work.  A similar situation was reported to IRS executives in December 2001, but it was not communicated to the site before computer replacement occurred.  An updated configuration of the Microsoft Internet Explorer software that was being tested as of June 3, 2002, is expected to address Internet-related access problems encountered during the hardware replacement process.

By not identifying, documenting, and communicating lessons learned during the computer replacement process, the HRPO risks negatively affecting additional employees at sites scheduled to receive replacement computers.  The HRPO stated that it had not formally documented lessons learned because HRPO personnel were informally documenting them through manual notes, but management was unable to provide us a copy of the notes.  The HRPO has commented that it plans to begin documenting lessons learned for use in future refreshment hardware rollouts.  The HRPO cited that another lesson learned that has not yet been documented is to increase upfront communication and obtain earlier business unit involvement at each site in deciding who needs a new computer and whether it should be a desktop or laptop.

Recommendations

The Deputy Commissioner for Modernization & Chief Information Officer should ensure:

1.      Post-installation conference calls are held to identify lessons learned during site installations.

Management’s Response:  After each refreshment deployment, the HRPO will ensure offices hold post-implementation conference calls to officially close the deployment.  The HRPO will also create a log to record its post-installation conference calls.

2.      Lessons learned are formally documented and effectively communicated to future computer replacement sites.

Management’s Response:  The HRPO will update the Lessons Learned document with issues that may affect future site installations and ensure the document is available to MITS Services employees and customers on the Hardware Refreshment web page for information.  The HRPO will also record in the log when members of its staff update the Lessons Learned document.

 

Appendix I

 

Detailed Objective, Scope, and Methodology

 

The overall objective of this audit was to evaluate the effectiveness of the Hardware Refreshment Program (HRP).  To accomplish this objective:

        I.            We interviewed Hardware Refreshment Program Office (HRPO) staff.  We also obtained and reviewed program management documentation including meeting minutes, the Management Plan, Business Performance Reviews, business case information, the Work Breakdown Structure, and the Deployment (Hardware Refreshment) Schedule.  We determined the extent of any documented and communicated lessons learned from post-implementation reviews.  We determined whether there was a methodology in place to measure and quantify HRP benefits.  We obtained and reviewed budget information and documentation.

     II.            We reviewed the HRPO’s Deployment (Hardware Refreshment) Schedule and a Projected Refreshment Summary detailing the business units at each site and judgmentally selected 4 of 28 sites to visit.  We selected the four sites because they had recently completed or were in the process of completing computer replacement activities.  In our site selection, we also considered the number and variety of business units projected to receive replacement computers.  At each site, we interviewed business unit employees to evaluate the effectiveness of the HRPO’s activities related to educating personnel about the computer replacement process and training on the new computers.  Finally, we evaluated the effectiveness of the rollout of the new computers and accompanying software in meeting business unit requirements and user needs.

 

Appendix II

 

Major Contributors to This Report

 

Scott E. Wilson, Assistant Inspector General for Audit (Information Systems Programs)

Gary Hinkle, Director

Danny Verneuille, Audit Manager

Myron Gulley, Senior Auditor

Mark Carder, Auditor

Linda Screws, Auditor

Tina Wong, Auditor

 

Appendix III

 

Report Distribution List

 

Commissioner  N:C

Deputy Commissioner  N:DC

Commissioner, Large and Mid-Size Business Division  LM

Commissioner, Small Business/Self-Employed Division  S

Commissioner, Tax Exempt and Government Entities Division  T

Commissioner, Wage and Investment Division  W

Chief, Information Technology Services  M:I

Director, End User Equipment and Services  M:I:EU

Chief Counsel  CC

National Taxpayer Advocate  TA

Director, Legislative Affairs  CL:LA

Director, Office of Program Evaluation and Risk Analysis  N:ADC:R:O

Office of Management Controls  N:CFO:F:M

Audit Liaisons:

            Deputy Commissioner for Modernization & Chief Information Officer  M

Chief, Information Technology Services  M:I

Director, End User Equipment and Services  M:I:EU

Office of Program Oversight and Coordination  M:R:PM:PO

 

Appendix IV

 

Management’s Response to the Draft Report

 

The response was removed due to its size.  To see the complete response, please go to the Adobe PDF version of the report on the TIGTA Public Web Page.