Audit of the Asset Seizure and Forfeiture Program Contract
September 2004
Reference Number:
2004-10-174
This report has cleared the Treasury
Inspector General for Tax Administration disclosure review process and
information determined to be restricted from public release has been redacted
from this document.
September
21, 2004
MEMORANDUM FOR
CHIEF, AGENCY-WIDE SHARED SERVICES
FROM: Gordon C. Milbourn III /s/ Gordon C.
Milbourn III
Acting Deputy Inspector
General for Audit
SUBJECT: Final Audit Report - Audit of the Asset
Seizure and Forfeiture Program Contract (Audit # 200410009)
This
report presents the results of our review of the Asset Seizure and Forfeiture
Contract. The overall objective of this
review was to determine whether the contractor billed the Internal Revenue
Service (IRS) accurately and according to the contract’s terms and
conditions.
Contract
expenditures represent a significant outlay of IRS funds. The Treasury Inspector General for Tax
Administration has made a commitment to perform audits of these
expenditures. As a result, we initiated
this audit to review the contractor’s invoices and determine whether the IRS
was billed accurately and according to the contract’s terms and conditions.
In
summary, the contractor’s documentation was not adequate to support all of the
costs invoiced to the IRS. Specifically,
we identified $99,613.40 of the $4.5 million in direct invoiced costs included
in our sample for which either the contractor was unable to provide any
supporting documentation, or the documentation was not adequate to support the
costs. We did not identify any
unallowable expenses.
We
recommended the Director, Procurement, seek recovery of the unsupported costs
of $99,613.40 unless the contractor provides acceptable support for those
costs.
Management’s
Response: IRS management agreed with the recommendation
presented in our report and initiated corrective action. Specifically, the contracting officer (CO)
held further discussions with the contractor and received additional
documentation to support $88,767.42 of the questioned labor and travel
expenses. The CO will initiate action to
recover the remaining unsupported amount of $10,845.99.
Office of Audit Comment:
We reviewed the additional documentation provided by the contractor to the
IRS. We were able to verify $85,781.30
of our original $99,613.40 of questioned costs.
However, we do not believe the contractor provided sufficient additional
documentation to support some of the travel expenses. The CO should consider this when seeking
recovery of all unsupported costs, totaling $13,832.10.
Please contact
me at (202) 622-6510 if you have any questions or Daniel R. Devlin, Assistant
Inspector General for Audit (Headquarters Operations and Exempt Organizations
Programs), at (202) 622-8500.
Documentation
Was Not Adequate to Support All of the Invoiced Costs
Appendix
I – Detailed Objective, Scope, and Methodology
Appendix
II – Major Contributors to This Report
Appendix
III – Report Distribution List
Appendix IV
– Outcome Measures
Appendix V – Management’s Response to the Draft Report
In September 1999, the Internal Revenue Service (IRS) awarded a time and materials contract for the Criminal Investigation (CI) function’s asset seizure and forfeiture program. The contractor provides support services to the asset forfeiture program, including personnel, supervision, and other related services, and incidental items necessary for the management of seized and forfeited assets.
The contract was awarded for a 1-year base period, with 4 option years. According to the IRS Request Tracking System, as of December 2003, the IRS had approved for payment approximately $10 million.
Because contract expenditures represent a significant outlay of IRS funds, the Treasury Inspector General for Tax Administration (TIGTA) has made a commitment to perform audits of these expenditures. We initiated this audit to review the contractor’s invoices and determine whether the IRS was billed accurately and according to the contract’s terms and conditions.
The review was performed in the Procurement directorate
within the Office of Agency-Wide Shared Services in
The audit was conducted in accordance with Government Auditing Standards. Detailed information on our audit objective, scope, and methodology is presented in Appendix I. Major contributors to the report are listed in Appendix II.
The contractor’s documentation was not adequate to support all of the costs invoiced to the IRS. Using a judgmental sample of 21 invoices, totaling approximately $4.5 million, we examined the contractor’s supporting documentation to verify charges for employee labor hours, as well as travel expenses. We identified $99,613.40 (2.2 percent) of the $4.5 million in direct invoiced costs included in our sample for which either the contractor was unable to provide any supporting documentation or the documentation was not adequate to support the cost. We did not identify any unallowable expenses.
Table 1 summarizes the questioned costs identified during our review.
Table 1:
Schedule of Questioned Costs
Questioned Activity
|
Questioned Cost
|
|---|---|
|
No documentation to support
labor hours invoiced |
$83,753.89 |
|
No documentation to support
travel expense |
$15,646.86 |
|
Overcharge of travel
expense due to miscalculation |
$212.65 |
Total
|
$99,613.40 |
Source:
TIGTA analysis of 21 invoices submitted to the IRS.
The Federal Acquisition Regulation (FAR) stipulates that a contractor is responsible for accounting for costs appropriately and for maintaining records, including supporting documentation, adequate to demonstrate that costs claimed have been incurred. The FAR also provides that costs shall be allowed to the extent they are reasonable, allocable, and allowable under the FAR.
The IRS has a process in place to verify the charges included on the invoices. While the contracting officer (CO) is the ultimate authority on administering the contract, the contracting officer’s technical representative (COTR) is the designated official for verifying the accuracy of the labor and travel expenses reported on the contractor’s invoices. The COTR relies on the CI function’s asset forfeiture coordinators (AFC) to verify the contractor’s labor hours. The AFCs are responsible for reviewing contractor employee timecards to ensure labor hours are being reported accurately. Additionally, an assistant COTR is responsible for evaluating travel expenses. This consists of a spot check for accuracy and proper authorization. However, the assistant COTR does not routinely review receipts for the travel vouchers.
Because we were unable to verify all the costs included on the invoices, there is no assurance the contractor billed the IRS accurately. Although our review identified only 2.2 percent in unsupported costs, it would be good practice for the IRS to randomly select charges at irregular intervals to verify to supporting documentation (e.g., time reports, travel receipts) as part of its invoice review process for all contracts.
1. The Director, Procurement, should seek recovery of the $99,613.40 in unsupported costs unless the contractor provides acceptable support for those costs.
Management’s Response: The CO held further discussions with the
contractor and received additional documentation to support $88,767.42 of the
questioned labor and travel expenses.
The CO will initiate action to recover the remaining unsupported amount
of $10,845.99.
Office of Audit Comment: We reviewed the additional documentation provided
by the contractor to the IRS. We were
able to verify $85,781.30 of our original $99,613.40 of questioned costs. However, we do not believe the contractor
provided sufficient additional documentation to support $2,986.11 in travel
expenses. The CO should consider this
additional amount when seeking recovery of all unsupported costs, totaling
$13,832.10.
Appendix I
Detailed
Objective, Scope, and Methodology
The overall objective for this review was to determine whether the contractor billed the Internal Revenue Service (IRS) accurately and according to the contract’s terms and conditions. We accomplished this objective by determining whether contractor billings were adequately supported and all costs were allowable. Specifically, we:
I.
Determined whether
labor hours, labor categories and rates, and travel costs billed were
allowable, accurate and supported by appropriate documentation, and consistent with
contract terms and conditions.
A.
Reviewed the IRS
contract files to identify all applicable contract terms and conditions and
determined the minimum contract qualifications required for each labor category
and corresponding labor rates.
B.
Interviewed IRS personnel
involved in the administration of the contract and payment of the invoices to
determine whether concerns exist regarding the contractor, its billing
practices, or any specific invoices.
C.
Prepared a sampling
plan and judgmentally selected a sample of invoices. A judgmental sample was used because we did
not plan to project the results to the universe. We analyzed all 33 of the contractor’s
invoices submitted from January 2001 through August 2003 to select our
sample. We selected a sample of 21 invoices
to verify all direct costs, including labor hours and travel expenses (e.g.,
airfare, hotel, mileage). Our sample
covered approximately $4.5 million (almost 65 percent) of the nearly $6.9
million in total invoiced expenses. In
addition, the sample included nearly $174,000 (nearly 55 percent) of the
approximately $317,000 in invoiced travel expenses.
1.
Traced employee hours
billed to supporting timesheets and payroll records to verify accuracy.
2.
Compared the labor
rates billed to those established in the contract to verify consistency with
the contract terms.
3.
Determined whether all
charges were allowable in accordance with the contract terms and Federal
Government regulations.
II.
Identified control
deficiencies that allowed the payment of invoices containing inaccurate,
unsupported, and/or unallowable labor and travel costs to occur. We did not review the contractor’s entire
systems of internal controls.
Appendix II
Major Contributors to This
Report
Daniel R.
Devlin, Assistant Inspector General for Audit (Headquarters Operations and
Exempt Organizations Programs)
John R.
Wright, Director
Debra Gregory, Audit Manager
Gary Pressley, Lead
Auditor
Robert Beel, Senior
Auditor
Chinita Coates, Auditor
Melvin Lindsey,
Auditor
Niurka Thomas, Auditor
Appendix III
Commissioner C
Office of the
Commissioner – Attn: Chief of Staff C
Deputy Commissioner
for Operations Support OS
Deputy Commissioner for Services and Enforcement SE
Chief, Criminal Investigation SE:CI
Director, Procurement OS:A:P
Chief Counsel CC
National Taxpayer Advocate TA
Director, Office of Legislative Affairs CL:LA
Director, Office of Program Evaluation and Risk Analysis RAS:O
Office of Management Controls OS:CFO:AR:M
Audit Liaisons:
Chief, Agency-Wide Shared
Services OS:A:F
Chief, Criminal Investigation SE:CI:S:PS
Director, Procurement OS:A:P
Appendix IV
This appendix presents detailed information on the measurable impact that our recommended corrective action will have on tax administration. This benefit will be incorporated into our Semiannual Report to the Congress.
Type and Value of Outcome Measure:
· Cost Savings, Questioned Costs (Unsupported) – Potential, $13,832.10 (see page 1).
Methodology Used to Measure the Reported Benefit:
To determine the questioned costs, we reviewed a judgmental sample of 21 invoices, including the corresponding supporting documentation. We selected our sample from a total population of 33 invoices the contractor submitted to the Internal Revenue Service (IRS) for services rendered during our review period (January 2001 through August 2003). We identified $99,613.40 in costs for which the contractor was either unable to provide any supporting documentation or the documentation was not adequate to support the cost.
The IRS’ response to the draft report provided that the contracting officer (CO) received additional documentation from the contractor and determined that $88,767.42 of the questioned costs were supported. Additionally, the IRS stated that the CO will initiate action to recover the remaining unsupported amount of $10,845.99.
We
reviewed this additional documentation and were able to verify $85,781.30 of
our original $99,613.40 of questioned costs.
However, we do not believe the contractor provided sufficient additional
documentation to support $2,986.11 in travel expenses. The contractor provided documentation that
the contractor believed supported $5,013.52 in travel expenses, but we concur
with only $2,027.41. The CO should
consider this when seeking recovery of all unsupported costs, totaling
$13,832.10.
Appendix V
Management’s Response to the Draft Report
The response was
removed due to its size. To see the
response, please go to the Adobe PDF version of the report on the TIGTA Public
Web Page.