The Custodial Accounting Project Team Is Making Progress;
However, Further
Actions Should Be Taken to Increase the Likelihood of a Successful
Implementation
March 2004
Reference
Number: 2004-20-061
This report has cleared the Treasury
Inspector General for Tax Administration disclosure review process and
information determined to be restricted from public release has been redacted
from this document.
March
3, 2004
MEMORANDUM FOR
CHIEF INFORMATION OFFICER
FROM: Gordon C. Milbourn III /s/ Gordon C. Milbourn
III
Acting Deputy Inspector
General for Audit
SUBJECT: Final Audit Report - The Custodial
Accounting Project Team Is Making Progress; However, Further Actions Should Be Taken to Increase the
Likelihood of a Successful Implementation (Audit # 200320025)
This report presents the
results of our review of the Custodial Accounting Project (CAP) Release
1.0. The overall objective of this
review was to assess the status of the Internal Revenue Service’s (IRS) and the
CAP contractor’s readiness to deliver the CAP Release 1.0. To accomplish our objective, we reviewed
test planning and execution, transition planning, and business continuity
planning activities. In addition, we
reviewed any deviations from cost and schedule estimates.
In summary, financial
accountability has proven to be problematic Government-wide. The Office of Management and Budget
considers 85 percent of major Federal Government agencies, including the
Department of the Treasury, to have serious problems with financial
accountability. Part of the IRS’ solution for correcting its
financial management weaknesses includes developing and implementing the CAP.
The IRS and the CAP
contractor have made progress toward implementing the CAP Release 1.0. The CAP team has planned a series of tests
to determine if the system will operate within expectations, completed
significant parts of the planned testing, and made some important transition
decisions. While the team has made
progress, it faces challenges in the following areas: testing, transition planning, and business continuity planning.
To
assist the IRS in facing these challenges, we recommended that the Chief
Information Officer (CIO) follow through on plans to increase the Business
Systems Modernization Office’s involvement in testing, ensure the CAP
contractor revises test scripts for future tests, and enhance transition
planning by reviewing newly published guidelines. We also recommended that the CIO build out and test the CAP
disaster recovery environment as soon as possible, and reconsider the CAP
disaster recovery classification.
In addition to challenges in
these three areas, the CAP contractor has experienced significant cost
increases and schedule delays. To
understand the reasons for this, we categorized the causes of each cost
increase and schedule delay. Since the IRS is in the process of
implementing previous recommendations concerning cost and schedule increases
and the use of firm fixed price contracts, we made no additional
recommendations in these areas.
Because the CAP team is in
the midst of critical testing and transition activities, we communicated the
results of our analyses intermittently during the audit. Therefore, this report is historical in
nature and may not reflect the most current activities or processes. We plan to conduct a follow-up audit to
provide additional analyses and recommendations as the CAP team works toward
implementation.
Management’s Response: Management
fully agreed with four of our recommendations and disagreed with one
recommendation. The IRS responded that
it has already established an embedded testing team with representatives from
the CAP and the MITRE Corporation to further enhance the CAP testing process. In addition, IRS management plans to ensure
revised test procedures are included in an upcoming contract, update the
Transition to Support Plan to incorporate transition acceptance criteria and
critical success factors, share the program-level disaster recovery strategy
with the CAP contractor, and ensure the contractor develops a project-level
disaster recovery plan. Management’s complete
response to the draft report is included as Appendix V.
Office of Audit Comment: The CIO
disagreed with our recommendation to reconsider the CAP disaster recovery
classification. The CIO stated that it
was the Chief Financial Officer’s (CFO) decision as owner of the system to
determine the criticality of the system, and the CFO had chosen the noncritical
classification. We understand the
responsibility for determining the CAP classification for disaster recovery
purposes may rest within another part of the IRS; however, we still believe the
IRS should reconsider the noncritical disaster recovery classification.
The noncritical classification means that, if the CAP
goes down after a disaster, the system could be down until restoration of the
disaster location or until a new system is purchased. The CAP Release 1.0 will support one of the IRS’ mission critical
processes. In addition, the General
Accounting Office has stated that one of the biggest obstacles facing IRS
management is the lack of financial management systems that can produce
information needed for day-to-day decisions.
In the event of a disaster, the CAP will not be restored timely to
support a mission critical process and to provide financial data for day-to-day
decision making. While we still believe our
recommendation is worthwhile, the IRS could change the classification of the
system in the future. Therefore, we do
not intend to elevate our disagreement concerning this matter to the Department
of the Treasury for resolution.
Copies of this report are
also being sent to the IRS managers affected by the report
recommendations. Please contact me at
(202) 622-6510 if you have questions or Margaret E. Begg, Assistant Inspector
General for Audit (Information Systems Programs), at (202) 622-8510.
The Custodial Accounting Project
Team Is Making Progress
Additional Focus Is Needed to Monitor Testing Results
Transition Planning Can Be Improved
Business Continuity Risks Need to Be Addressed
Cost Increases and Schedule Delays Persist
Appendix
I – Detailed Objective, Scope, and Methodology
Appendix
II – Major Contributors to This Report
Appendix III – Report Distribution List
Appendix V – Management’s Response to the Draft Report
The Custodial Accounting Project (CAP) will be a single, integrated data repository of taxpayer account information, integrated with the general ledger and accessible for management analysis and reporting. The first release of the CAP will extract taxpayer account data from the Individual Master File (IMF) for the Taxpayer Account Subledger. The second release of the CAP will extract data from the Business Master File (BMF) and other sources for the Taxpayer Account Subledger.
Financial accountability has proven to be problematic Government-wide. The Office of Management and Budget considers 85 percent of major Federal Government agencies, including the Department of the Treasury, to have serious problems with financial accountability. Weaknesses in the Internal Revenue Service’s (IRS) financial management systems include:
· Deficiencies in controls to properly manage unpaid assessments, which result in both taxpayer burden and lost revenue to the Federal Government.
· Deficiencies in controls over tax refunds, which permit the disbursement of improper refunds.
· Inadequacies in the financial reporting process, which limit the timeliness and reliability of information for decision making.
These weaknesses have caused the IRS to expend tremendous resources to prepare reliable financial statements. Additionally, these weaknesses may adversely affect any decision by IRS management and/or the Congress that is based upon information obtained from IRS systems.
Part of the IRS’ solution for correcting these financial management weaknesses includes developing and implementing the CAP. During our audit, the CAP team was making progress in preparing for implementation by planning and executing significant testing and making significant transition decisions. While the CAP team has made progress, it faces challenges to improve testing, transition planning, and business continuity planning. In addition, progress has been more costly and slower than planned.
The Business Systems Modernization Office (BSMO) and the CAP contractor were making changes to CAP testing activities during our review period. Changes that have occurred since we concluded our analysis in early November 2003 are not reflected in this report. As a result, this report may not reflect the most current activities or processes. We plan to conduct a follow-up audit to assess the progress being made toward implementing the CAP Release 1.0.
This review was performed at the BSMO facilities in IRS National Headquarters and New Carrollton, Maryland, and the CAP contractor offices in Merrifield, Virginia. To provide timely feedback during critical testing activities, we communicated the results of our analyses intermittently during the audit. These communications are discussed throughout the report.
The audit was conducted between January and December 2003 in accordance with Government Auditing Standards. Detailed information on our audit objective, scope, and methodology is presented in Appendix I. Major contributors to the report are listed in Appendix II.
In August 2000, the CAP team was approved to move forward with the development, testing, and implementation of the CAP. During our audit, the IRS and the CAP contractor were testing the system and preparing for implementation.
The IRS and the CAP contractor have made progress testing and preparing CAP Release 1.0 for implementation. The team has planned a series of tests to determine if the system will operate within expectations, completed significant parts of the planned testing, and made some important transition decisions.
Testing plans were prepared
The CAP team has prepared a complementary set of test plans to help ensure that the developed system meets expectations. We reviewed plans for the following test phases and found that the plans generally followed the standards set forth in the Enterprise Life Cycle (ELC).
· System Integration Test (SIT) – Ensures that system components are properly integrated. More specifically, this test ensures the components of the system can properly exchange information with each other and with other systems.
· System Acceptance Test (SAT) – Confirms that the overall system functions correctly from the end user’s point of view.
· Release System Integration and Test (RSIT) – Verifies that the CAP can properly integrate with other designated modernization projects.
Each test plan included entrance and exit criteria, specific test procedures to be followed, and the expected results for each test procedure.
Significant testing has been completed or is in
progress
During our audit work, the CAP team completed the SIT for the CAP Release 1.0. In addition, the CAP team started the SAT and RSIT.
Important transition decisions were made
A Transition To Support (T2S) Plan includes the information necessary to successfully migrate a system to the IRS environment. The CAP T2S Plan was initially due in June 2002; however, it could not be completed at that time because a decision had not been made as to who would maintain and operate the CAP once Release 1.0 was deployed.
In Spring 2003, the IRS decided that the CAP contractor would maintain the system, while the IRS Enterprise Operations Office would operate the system. In addition, funds from the Information Systems appropriation would be used to pay for operations and maintenance costs. Once the IRS had communicated these decisions, the CAP contractor delivered a draft version of the CAP T2S Plan in July 2003 for review.
As mentioned previously, significant testing has been completed or is underway. The most formal testing that has been completed is the SIT. Therefore, the majority of our efforts involved analyzing the SIT.
We reviewed the test results from the 6 completed SIT scripts (consisting of 425 test procedures) to determine whether all test results were accurately reported and all test procedures were actually performed. We found the following:
· Testing officials reported inaccurate test information during critical meetings. The ELC requires that meetings be held to determine if a project team is ready to proceed from one test phase to another. The CAP team correctly held these meetings. However, testing officials reported inaccurate information during these meetings.
First, testing officials reported that seven of eight test scripts had passed the SIT. In actuality, only six of the eight test scripts had passed the SIT. The remaining two test scripts were deferred until the SAT.
In addition, testing officials reported that only two problem reports were outstanding upon exiting the SIT. Using a file of problem reports dated September 25, 2003, we identified an additional eight problem reports that were outstanding after the SIT had concluded. We reported this to the BSMO on November 9, 2003. The CAP contractor responded that these problem reports were not discussed during critical meetings because short-term solutions had been applied to fix the problems, documentation was incorrect and the problems were not outstanding, or the intention was to fix the problem as part of the SAT.
· The CAP contractor did not always complete the test procedures as written. Therefore, the actual testing results did not always match the predetermined expected results. We identified 24 test procedures that could not be completed as written. The CAP contractor informed us that this occurred for several reasons: lack of sufficient data in the SIT environment, lack of systems software in the SIT environment, and lack of data to generate logs and reports.
We also identified 23 planned test procedures that were either not applicable or for which alternative test procedures were conducted. Testers determined certain test procedures were not applicable, could be accomplished more efficiently, or needed additional instructions. The ELC states that testers should correct test procedures as problems are discovered. However, the test procedures were not corrected. We communicated these concerns to the BSMO on September 24, 2003.
· Some test procedures were not updated with actual test results. Some test procedures failed initially. Once retested, the test procedures passed. However, the actual results were not updated in the testing documentation for seven test procedures. We communicated this concern to the BSMO on September 24, 2003.
We determined these inaccuracies had little effect on the
project because the IRS and the CAP contractor can ensure shortfalls from the
SIT are handled as part of the SAT.
However, it will be important to ensure that all testing results are
known prior to completing the SAT. The IRS CAP Project Manager
informed us that she was not initially aware of detailed test result
inaccuracies due to staffing shortages.
Management Actions: Once we conveyed our SIT concerns to the CAP contractor, the contractor stated it would 1) ensure all closed SAT test records are reviewed before problem reports are closed, 2) correct test procedures that would be reused in a later set of tests known as the Deployment Site Readiness Test (DSRT), 3) update testing documentation with actual testing results, and 4) update testing results to make the test results clearer. The CAP contractor also prepared documentation to defer the testing of 49 test procedures from the SIT phase to the SAT phase.
The IRS CAP Project Manager informed us that the BSMO was concerned about the inaccuracies in reporting test results, but she was comfortable with the corrections being made by the CAP contractor. With additional staffing now available, the IRS CAP Project Manager also informed us that she has assigned BSMO and MITRE representatives to enhance oversight and reduce risk in this area.
To improve insight into the testing process and results, the
Chief Information Officer (CIO) should:
1.
Continue
increased involvement by BSMO and/or MITRE officials in the CAP testing
process.
Management’s Response: The IRS responded that it has already established an embedded
testing team with representatives from the CAP and MITRE to further enhance the
CAP testing process. In addition, CAP
and MITRE support will continue through Milestone 5.
2.
Ensure the CAP contractor follows
through on plans to revise test procedures for the DSRT.
Management’s Response: IRS management plans to ensure revised DSRT procedures are
included in an upcoming contract.
The CAP contractor recently
delivered a draft version of the CAP T2S Plan to document how the system will
migrate from the CAP contractor to the IRS.
We reviewed a draft version of the CAP T2S Plan and determined it
complied with ELC requirements.
However, it could be improved by applying transition best practices.
Recently, the PRIME contractor
enhanced the ELC to require a Transition Management Plan, in place of a T2S
Plan. The Transition Management Plan
guidance is a result of the accumulation of best practices by the PRIME
contractor. Since the CAP team started
development prior to creation of the new requirement, it is not required to
deliver a Transition Management Plan.
The CAP team could improve
transition planning by reviewing the revised ELC guidance and determining if
adhering to any additional requirements would improve the CAP T2S Plan. In particular, the requirements for
transition acceptance criteria and critical success factors would be helpful in
planning the CAP transition. Since the
final CAP T2S Plan was due to the IRS for review in early December 2003, we
communicated this improvement opportunity to the BSMO on October 16, 2003.
To enhance transition planning,
the CIO should:
3.
Determine if any sections of
the new ELC guidelines could be applied to the draft CAP T2S Plan to make the
Plan more comprehensive. For example,
the project team should consider incorporating transition acceptance criteria
and critical success factors.
Management’s Response: The IRS responded that it had met with the CAP contractor to
convey the need to review the new ELC guidelines and determine whether best
practice recommendations would produce a more comprehensive CAP T2S Plan. In addition, the CAP contractor will update
the T2S Plan to incorporate transition acceptance criteria and critical success
factors.
The IRS’ business continuity program includes disaster
recovery, business resumption, and other related efforts to ensure IRS
operations continue in the event of an unexpected outage. For the CAP, we determined several risks
need to be addressed to ensure CAP operations can continue in such an
event. We communicated our concerns to
the BSMO on August 1, 2003.
Disaster recovery
capabilities will not be built out or fully tested prior to implementation
In case of a disaster after system implementation, certain components needed to fully restore CAP functionality are not currently available. For example, a mid-level computer system that will be used to log into the CAP application has not been replicated at a disaster site.
According to BSMO officials, funds have been earmarked for the next 2 fiscal years to improve disaster recovery capabilities for all modernization projects. Until that time, disaster recovery capabilities will be less than optimal. Until all components needed for a full restoration of CAP capabilities are put in place, a full test of disaster recovery capabilities cannot be conducted. According to project officials, not having full disaster recovery capabilities was caused by past budget cuts.
Without full disaster recovery capabilities and testing, the IRS runs the risk that the CAP will not be able to fully recover in the event of a disaster. According to IRS officials, this risk is minimized because the majority of the CAP application runs in a mainframe environment, which can be restored in the event of a disaster.
Business contingency
tests were not initially conducted
The SIT Plan defines two tests known as the Application Recovery Test and the Technical Recovery Test that were to be conducted at the Martinsburg Computing Center. These tests would provide indicators of the CAP’s ability to recover adequately from various simulated system failures. We determined that these tests were not conducted because the CAP contractor did not inform the Martinsburg Computing Center these tests needed to be conducted.
Management Action: Upon being informed these tests had not been conducted, the CAP contractor rescheduled the tests for the SAT.
CAP Release 1.0 is
currently classified as a noncritical system
The draft CAP Technical Contingency Planning Document describes the contingency planning framework and identifies strategies for recovery in the event of a disaster. Our review of the draft CAP Technical Contingency Planning Document revealed that the CAP Release 1.0, a system that will cost taxpayers nearly $100 million, was classified as a noncritical system. This classification means that if the CAP goes down after a disaster, the system could be down until restoration of the disaster location or until a new system is purchased.
We asked Chief Financial Officer (CFO) and BSMO personnel why the CAP was classified as noncritical. Based upon information from the personnel we interviewed, we could not determine the exact reason for the classification. However, a CAP team member informed us that the CAP would not be relied upon to prepare financial statements during Fiscal Year 2004 and that the classification could be changed at any time in the future. This, along with the fact that the IRS has been able to sustain a clean opinion on its financial statements without the CAP, may be the reason the system is currently considered noncritical.
Notwithstanding these points, we determined that the CAP Release 1.0 will support one of the IRS’ mission critical processes – preparing audited figures for unpaid assessments, tax receipts, and refunds. Therefore, we believe the IRS should consider upgrading the CAP’s classification as the CAP moves toward implementation.
To ensure IRS officials are able to restore the CAP after a disaster with the least disruption to the IRS mission, the CIO should:
4.
Completely build out and test
the CAP disaster recovery environment as soon as possible.
Management’s Response: IRS management plans to share the program-level disaster recovery
strategy with the CAP contractor and ensure the contractor develops a
project-level disaster recovery plan.
5. Reconsider the CAP disaster recovery classification in the draft Technical Contingency Planning Document.
Management’s Response: The CIO disagreed with our recommendation to reconsider the CAP disaster recovery classification. The CIO stated it was the CFO’s decision as owner of the system to determine the criticality of the system, and the CFO had chosen the noncritical classification.
Office of Audit Comment: While we understand the responsibility for determining the CAP classification for disaster recovery purposes may rest within another part of the IRS, we still believe the IRS should reconsider the noncritical disaster recovery classification. The noncritical classification means that, if the CAP goes down after a disaster, the system could be down until restoration of the disaster location or until a new system is purchased. The CAP Release 1.0 will support one of the IRS’ mission critical processes. In addition, the General Accounting Office has stated that one of the biggest obstacles facing IRS management is the lack of financial management systems that can produce information needed for day-to-day decisions. In the event of a disaster, the CAP will not be restored timely to support a mission critical process and provide financial data for day-to-day decision making. While the current disaster recovery classification is noncritical, the IRS could change the classification of the system in the future.
In a previous audit, we reported
the estimated costs to complete the first release of the CAP had increased from
a planned $47 million to over $61 million.
In addition, the schedule for implementation had slipped from May 2002
until May 2003. Cost increases and
schedule delays have continued since that audit.
The majority of the cost increases noted during our previous audit were due to a work stoppage beginning in late 2000. In September 2000, the Congress directed the BSMO to limit spending on the CAP until deficiencies in the CAP business case were corrected and the management of the CAP was integrated with the Business Systems Modernization (BSM) program.
During this audit, we determined that costs have continued to increase. The latest published cost to complete the CAP Release 1.0 is now nearly $98 million. The vast majority of this increase continues to be due to integrating with the BSM program. Based upon our review of documentation and discussions with project officials, we categorized the many different cost increases since our previous review into the following general categories. See Appendix IV for a delineation of all cost increases and how each cost increase was categorized.
Breakout
of Cost Increases Since Our Previous Audit
The chart was
removed due to its size. To see the
chart, please go to the Adobe PDF version of the report on the TIGTA Public Web
Page.
Schedule increases
At the end of our previous audit, the CAP Release 1.0 was due to exit Milestone 5 in May 2003. At the time we completed our fieldwork, the Milestone 5 exit date had been re-scheduled for February 2004. This is a 9-month slippage in completing the CAP Release 1.0 since our previous review. The causes of the schedule slippage are similar to the causes of the cost increases detailed previously.
Future cost and schedule increases
At the end of our review, the CAP contractor was replanning
the amount of time that would be needed to complete testing for the CAP Release
1.0. Due to the contract type, any
additional time needed to complete Release 1.0 will require additional funds
from the IRS. Since this information
was not available to us at the end of the audit, it was not included in the
previous analysis.
One of the reasons cost increases continue to mount for the Federal Government is that the CAP contractor is not operating under a firm fixed price contract. In the past, we have recommended firm fixed price contracts be used whenever possible, especially for projects in the development and deployment stages such as the CAP.
Management Actions: On September 29, 2003, the CIO issued a policy that states contracts for BSM projects be fixed price, with certain exceptions. As part of this policy statement, the CIO requested that the Associate Commissioner, BSM, and the Director, Procurement, provide plans for implementing the new policy.
Since the IRS is in the process of implementing previous recommendations concerning cost and schedule increases and the use of firm fixed price contracts, we are making no additional recommendations in these areas. We will consider following up on previous recommendations in the future.
Appendix I
Detailed Objective, Scope,
and Methodology
The overall objective of this review was to assess the status of the Internal Revenue Service’s (IRS) and the Custodial Accounting Project (CAP) contractor’s readiness to deliver the CAP Release 1.0. To accomplish our objective, we:
I. Determined whether project officials developed the project test plans in accordance with Enterprise Life Cycle (ELC) requirements.
II.
Determined
whether the CAP contractor accurately reported test results and resolved
documented problems.
A.
Compared
the test results to the test plans to determine whether all tests were
performed.
B.
Traced
summary test results to the detailed test results to determine whether the
summary test results were reported accurately.
C.
Determined
whether components that were scheduled for testing for the CAP Release 1.0 were
adequately addressed during the System Integration Test (SIT).
D.
Reviewed a
download of test failures for the SIT and determined whether failures were
adequately addressed. In addition, we
documented whether the IRS ensured the test failures were effectively
addressed.
III. Determined how the IRS plans to operate and maintain the CAP Release 1.0 after deployment.
A. Documented how the project team plans to resolve issues related to supporting the project after deployment.
B. Reviewed the draft Transition To Support Plan.
IV. Determined whether project officials were adequately planning for contingencies.
V.
Determined
the extent of changes to the project’s estimated cost, schedule, and/or
benefits and whether the changes had been adequately explained and supported.
NOTE: Additional work
was scheduled concerning the CAP System Acceptance Test (SAT) and project
dependencies. Due to delays in CAP
testing, we were unable to complete sufficient work to report on the CAP
SAT. Due to delays in other
modernization projects, we are also not reporting on project dependencies due
to their decreased significance for the CAP Release 1.0.
Appendix II
Major Contributors to This Report
Margaret E. Begg, Assistant Inspector General
for Audit (Information Systems Programs)
Gary V. Hinkle, Director
Scott A. Macfarlane, Director
Troy D. Paterson, Audit Manager
James A. Douglas, Senior Auditor
Wallace C. Sims, Senior Auditor
Tina Wong, Senior Auditor
Appendix III
Commissioner C
Commissioner – Attn: Chief of Staff C
Deputy Commissioner for
Operations Support OS
Associate Commissioner, Business
Systems Modernization OS:CIO:B
Deputy Associate Commissioner,
Program Management OS:CIO:B:PM
Acting Director, Portfolio
Management OS:CIO:R:PM
Director, Internal Management
Modernization OS:CIO:B:PM:IMM
Chief Counsel
CC
National Taxpayer Advocate TA
Director, Office of Legislative
Affairs CL:LA
Director, Office of Program Evaluation and
Risk Analysis RAS:O
Office
of Management Controls OS:CFO:AR:M
Audit Liaison: Associate Commissioner, Business Systems Modernization OS:CIO:B
Appendix IV
Breakout of Cost Increases for the Custodial
Accounting Project Since the Previous Audit
|
Description |
Amount of the Change |
|
Business
Systems Modernization Integration
|
|
|
|
Integration
With Security and Technology Infrastructure Release (STIR) Components |
$ 0.94 |
|
|
Integrated
Financial System (IFS) Analysis and Design Requirements |
$ 0.38 |
|
|
Custodial
Accounting Project (CAP) – Customer Account Data Engine (CADE) Interface
Development |
$ 2.80 |
|
|
6-Month
Schedule Extension, STIR/Infrastructure Shared Services Impact, etc. |
$ 7.47 |
|
|
IFS-CAP
Interface Implementation |
$ 1.51 |
|
|
Infrastructure
Shared Services Interim Solution |
$ 2.11 |
|
|
PRIME
Account Management |
$ 0.75 |
|
|
CADE
Interface |
$ 1.40 |
|
|
IFS
Business Warehouse (CAP Work) |
$ 0.25 |
|
|
IFS
Business Warehouse (IFS Work) |
$ 0.38 |
|
|
Modernized
Interface Changes (Fiscal |
$ 2.00 |
|
|
|
Subtotal |
$ 19.99 |
|
Current Processing
Environment Changes |
|
|
|
Changes
to the Individual Master File (IMF) Extract |
$ 0.48 |
|
|
Mid-Year
IMF Changes |
$ 0.12 |
|
|
Calendar
Year 2003 and Mid-Year 2003 IMF Return Transaction File (RTF) Changes |
$ 1.86 |
|
|
Mid-Year
Changes |
$ 0.45 |
|
|
|
Subtotal |
$ 2.91 |
|
Hardware/Software |
|
|
|
Additional
Hardware and Software |
$ 6.50 |
|
|
|
Subtotal |
$ 6.50 |
|
Transition Activities |
|
|
|
Enterprise
Operations Transition Support |
$ 0.35 |
|
|
Enterprise
Operations Support in FY 2003 |
$ 0.87 |
|
|
Operations
and Maintenance through |
$ 2.04 |
|
|
Enterprise
Operations FY 2004 Support through Milestone 5 |
$ 0.20 |
|
|
|
Subtotal |
$ 3.46 |
|
Other |
|
|
|
Cyber
Security |
$ 0.06 |
|
|
Payments Accounting
Claims Enhancements Reconciliation (PACER) – CAP Interface |
$ 1.60 |
|
|
Section
508 Compliance |
$ 0.10 |
|
|
Standards
Changes |
$ 0.50 |
|
|
Archive
Purge |
$ 0.15 |
|
|
Exhibit
300 |
$ 0.10 |
|
|
Management
Reserve |
$ 0.87 |
|
|
|
Subtotal |
$ 3.38 |
|
|
|
|
|
|
TOTAL |
$ 36.24 |
Source: Analysis based upon information provided by
the Business Systems Modernization Office.
Appendix V
Management’s Response to the Draft Report
The response was removed due to its size. To see the response, please go to the Adobe
PDF version of the report on the TIGTA Public Web Page.