TREASURY
INSPECTOR GENERAL FOR TAX ADMINISTRATION
Management Oversight Improved, but Expected Benefits and Capabilities for the Tax Exempt Determination System Release 2 Were Not Delivered
December 11, 2007
Reference Number: 2008-10-025
This report has cleared the Treasury Inspector General for Tax Administration disclosure review process and information determined to be restricted from public release has been redacted from this document.
Phone Number |
202-622-6500
Email Address | inquiries@tigta.treas.gov
Web Site |
http://www.tigta.gov
December 11, 2007
MEMORANDUM
FOR COMMISSIONER, TAX EXEMPT AND GOVERNMENT ENTITIES DIVISION
FROM: Michael R. Phillips /s/ Michael R. Phillips
Deputy Inspector General for Audit
SUBJECT: Final Audit Report – Management Oversight Improved, but Expected Benefits and Capabilities for the Tax Exempt Determination System Release 2 Were Not Delivered (Audit # 200610047)
This report presents the results of our review of the Tax Exempt
Determination System (hereafter referred to as the TEDS or System)[1] Release 2. The overall objectives of this review were to
determine whether the Tax Exempt and Government Entities (TE/GE) Division developed TEDS
Release 2
using sound
system development practices and whether it managed the Release 2
investment in compliance with Office of Management and Budget and Clinger-Cohen
Act of 1996[2] requirements. This audit was conducted as part of the
Treasury Inspector General for Tax Administration Office of Audit Fiscal Year
2007 Annual Audit Plan.
Impact on the Taxpayer
In September 2003,
TE/GE Division management began developing TEDS Release 2, which was to include
the upfront imaging of Employee Plans function and Exempt Organizations
function determination applications, enhanced reporting, and automated case
assignment. The System is currently
scheduled for implementation in May 2008.
However, when the System is completed, its cost may far outweigh its
benefits. The high cost of the TEDS
compared to the benefits it will deliver brings into question whether sound
investment decisions were made during development of the System and whether
this was the best use of Federal Government funds.
Synopsis
Overall, the TE/GE
Division Investment Executive Steering Committee improved its oversight of the
development of TEDS Release 2 from that provided during Release 1 by using
certain project management techniques. In addition, TE/GE Division management
began tracking some project costs as we had recommended.[3]
However, management did not fully implement our prior recommendations to
evaluate investment decisions and monitor whether business benefits would be
realized. We identified the following:
·
Schedule
delays and deletion of some system capabilities resulted in delivering only
$33.5 million (less than one-half) of the $73.1 million in expected benefits
included in the August 2004 Business Case.[4]
·
Total
project costs were not monitored and reported because TE/GE Division management
did not have a process in place to appropriately evaluate investment
decisions. The estimated contractor cost
was exceeded by $2.1 million (26 percent), and estimated internal labor costs
of $5.1 million were not tracked to the August 2004 Business Case. As a result, we could not verify the reliability
of $7.2 million in the Business Case.
·
Very
few benefits were received from the development of TEDS Release 1. Upon completion of Release 1, the technical
infrastructure, including computer hardware and software designed to support
all future System releases, was replaced because it did not meet new Internal
Revenue Service (IRS) standards. As a
result, an inefficient use of resources occurred when little benefit was
realized from the $17 million spent on Release 1.
· Project management oversight may not ensure TEDS Release 2 will align with future IRS systems and processes. Oversight is necessary to ensure additional costs are not incurred in the future to bring the applications into alignment with other systems.
Recommendations
We recommended the Commissioner,
TE/GE Division, ensure costs, schedule delays, and changes in system
capabilities on expected benefits are tracked and reviewed against business
cases. In addition, we recommended the
Director, Business Systems Planning, complete plans to improve the tracking of
actual Federal Government costs back to investments and provide this
information to the TE/GE Division Investment Executive Steering Committee for
review.
Response
The Commissioner, TE/GE Division, agreed with our recommendations and provided planned actions to address them. These actions include ensuring costs, schedule delays, and changes in system capabilities on expected benefit are tracked against business cases and actual Federal Government costs are tracked back to investments and provided to the TE/GE Division Investment Executive Steering Committee for review. However, IRS management disagreed with 1 of the 3 outcome measures described in the report ($17.0 million in inefficient use of resources). The Commissioner, TE/GE Division, stated the lack of success in a venture such as TEDS Release 1 does not equate to inefficiency. Instead, lessons learned from Release 1 helped form new IRS standards in Enterprise Architecture that were used in TEDS Release 2 and will be used in all future IRS projects.
In addition, the Commissioner, TE/GE Division, provided perspective on how the TE/GE Division manages systems development projects and how it experienced technical and other challenges in its work on the TEDS project. Management’s complete response to the draft report is included as Appendix VI.
Office of Audit Comment
We acknowledge the difficulty in managing a significant information technology project such as the TEDS project and believe the TE/GE Division’s commitment to make additional improvements through its stated corrective actions will improve oversight of future systems development projects. Furthermore, we agree that lessons learned did provide a benefit to the IRS; however, we believe there was little tangible benefit for the investment in TEDS Release 1. While we recognize the costs for TEDS Release 1 cannot be recovered at this point, increased controls over tracking costs, delays, or other system capabilities should help the IRS better monitor future projects and prevent implementation of new systems that are unable to accomplish their primary purposes.
In addition, the Commissioner, TE/GE Division, stated the TEDS project management team is working closely with the IRS Enterprise Architecture to comply with emerging standards as they apply to the TEDS and it is premature to conclude that Release 2 will not align with future Enterprise Architecture standards. We agree with the Commissioner’s conclusion and have made applicable wording changes to the report. However, we believe completing and approving required Enterprise Architecture documentation is a good preventive measure to ensure compliance with the future IRS Enterprise Architecture.
Copies of this report are also being sent to
the IRS managers affected by the report recommendations. Please contact me at (202) 622-6510 if
you have questions or Nancy A. Nakamura, Assistant Inspector General for Audit
(Headquarters Operations and Exempt Organizations Programs), at (202) 622-8500.
Appendices
Appendix
I – Detailed Objectives, Scope, and Methodology
Appendix
II – Major Contributors to This Report
Appendix
III – Report Distribution List
Appendix
IV – Outcome Measures
Appendix
V – Glossary of Terms
Appendix VI – Management’s
Response to the Draft Report
|
IRS |
Internal Revenue Service |
|
TEDS; System |
Tax Exempt Determination System |
|
TE/GE |
Tax Exempt and Government Entities |
The Tax Exempt and Government Entities (TE/GE) Division identified a
critical need to modernize and improve its processing of Employee Plans
function and Exempt Organizations function determination letter[5] applications. The Employee Plans/Exempt Organizations
Determination System in use at the time was an outdated technology that could
not handle the required workload, fulfill statutory Internal Revenue Service
(IRS) responsibilities under the Internal Revenue Code, and meet expectations
of Employee Plans function and Exempt Organizations function customers. In December 2001, the TE/GE Division
Investment Executive Steering Committee[6] approved a seven-stage release strategy for
the Tax Exempt Determination System (hereafter referred to as the TEDS or
System) to replace the Employee Plans/Exempt Organizations Determination System,
automate certain manual processes, and reduce or eliminate employee labor
expense.
The TEDS was needed to address several critical workload factors that
threatened to overwhelm the Employee Plans function and Exempt Organizations
function Determinations Programs.
·
Due to
several law changes, the TE/GE Division anticipated receiving a significant
increase in the number of employee plans restatement applications during Fiscal Years 2002
and 2003.
· The Determinations Programs were not effective or efficient. For example, the average time to work determination cases and the cycle time to respond to simple inquiries and status changes were too long; the level of accuracy for determinations was unacceptably low; expected peak volume demands could not be met; significant manual processes, paper handling, and tracking were inefficient; nonautomation of case grading, classification,[7] and assignment was inefficient; and postal costs were excessive because of an inefficient practice of mailing case files.
The Determinations Programs are a key part of the TE/GE Division and
the service provided to its customers.
Without tax-exempt status, plan sponsors may have to operate pension
plans without favorable tax treatment, and exempt organizations cannot give
donors tax-deductible receipts.
TEDS Release 1,
deployed in March 2004, was intended to provide the initial technical
infrastructure for all future System releases, redesign the process for some Employee Plans function customers requesting
determination letters,[8] reduce cycle time, and improve
customer satisfaction and determination letter quality. In September 2006, we reported[9] that many of the projected benefits were not
delivered and investments associated with the development of Release 1 were not
appropriately tracked, which prevented TE/GE Division senior management from
receiving the information needed to effectively evaluate their investment in
the System. The actual cost to develop,
implement, and maintain Release 1 (through February 17, 2006) was more than
$16.9 million, which was approximately $2.3 million higher than the estimate
made in the August 2003 TEDS Business Case.
However, this Business Case was not appropriately updated to reflect the
severely curtailed capabilities of the System, the 16 percent increase in cost,
and the 5‑month delay in delivery of the System. We recommended and TE/GE Division
management agreed to adopt a business case model that tracked and monitored the
actual project costs.
TE/GE Division Business Systems Planning function management started to
develop TEDS Release 2 in September 2003, and the Director, Exempt
Organizations, became the new executive owner in August 2005. Release 2 was to include the upfront imaging
of Employee Plans function and Exempt Organizations function determination
applications, enhanced reporting, and automated case assignment. It was originally scheduled for
implementation in March 2007. Release 2
implementation is currently scheduled for May 2008.
Project responsibilities for developing TEDS Release 2 are designated as follows:
·
The
TE/GE Division Investment Executive Steering Committee has overall
responsibility for approving the TEDS Business Cases used to request funding
for the new computer system, monitoring and overseeing development of the
project, and approving project requests to exit a milestone and continue with
development and delivery of the System.
The Committee also has a responsibility to stop the project, if
necessary, when the budget is exceeded or the success of the project is in
jeopardy.
· TEDS project management is responsible for managing project costs, schedules, and performance in accordance with IRS policy. This includes responsibility for acquisition and delivery of products or systems; ensuring the System complies with the IRS Enterprise Architecture; providing status information and recommendations to the TE/GE Division Investment Executive Steering Committee; and managing changes to costs, schedules, and requirements of the project.
This review was performed at the
TE/GE Division National Headquarters Business Systems Planning function and Exempt Organizations function offices
in
While Some Improvements Have Been Made, Management Oversight Did Not Ensure Significant Expected Savings Were Achieved and Expected Capabilities Were Delivered
The TE/GE Division
Investment Executive Steering Committee improved its oversight of the development of TEDS Release 2 from that
provided during Release 1 by using certain project management techniques. In addition, TE/GE Division management began
tracking some project costs as we had recommended.[10]
However, management did not fully implement our recommendations to
evaluate investment decisions and monitor whether business benefits would be
realized. As a result, when TEDS Release
2 is completed, its cost may far outweigh its benefits. The high cost of the System compared to the
benefits it will deliver brings into question whether sound investment
decisions were made during the System’s development and whether this was the
best use of Federal Government funds. We
identified the following:
·
Less
than one-half of the originally envisioned monetary benefits of Release 2 will
be delivered, and the cost of the Release may now exceed the benefits. At the end of our audit work, TE/GE Division
management provided some explanations for the change in value of individual
benefits listed in the February 2007 Business Case[11] and the impact schedule delays and deletion
of some system capabilities had on overall project benefits.
·
The
IRS exceeded by $2.1 million (26 percent) the estimated contractor cost and did
not track the estimated $5.1 million in internal labor costs in the August 2004
Business Case. As a result, we could not
verify the reliability of $7.2 million in the Business Case.[12]
·
TE/GE
Division management did not ensure required Enterprise Architecture
documentation was completed as required.
Therefore, there is no assurance that the System was designed and built
to work with other IRS computer systems to improve performance and productivity
without the need to make additional future changes.
·
We
previously reported that significant benefits from Release 1 were not realized
(i.e., reduced cycle times, improved customer satisfaction, and improved
customer service). However, in our
previous report, we did not comment on another significant benefit envisioned
for Release 1: providing the initial
technical infrastructure (hardware and software) for future releases. We determined this benefit was not realized
because computer hardware, software, and custom code were completely replaced
for Release 2. As a result, an
inefficient use of resources occurred when little benefit was realized from the
$17 million spent on Release 1.[13]
Certain project management techniques were
generally planned for and applied during development of the TEDS Release 2
The TE/GE Division Investment Executive Steering Committee improved its oversight of the development of Release 2 by using certain project management techniques. In previous reports concerning the development of Release 1,[14] we reported that project management techniques were not effectively used.
TE/GE Division
management adopted the Enterprise Life Cycle-Lite as a process to plan and
manage the development of Release 2. The
Enterprise Life Cycle-Lite is a disciplined system development methodology that uses reviews, checkpoints, and
milestones to ensure projects are efficiently and effectively planned,
designed, developed, and implemented.
TE/GE Division management planned for and generally implemented Enterprise
Life Cycle-Lite techniques. Those
techniques and management’s activities included:
·
Risk management –
Processes were developed to identify, quantify, respond to, and control
potential problems that could severely affect Release 2 development goals. We
reviewed risk reports that identified the critical status of potential
problems, as well as the actions identified to reduce the risk that the most
likely problems could occur.
· Configuration management – Processes were developed to identify, control, and approve changes to system documentation, computer source code, and off-the-shelf software.
· Requirements management – Processes were developed to gather and document requirements, track the design and programming to the requirements, and manage any changes.
·
Transition
management – Processes were developed to transition from the old
Employee Plans/Exempt Organizations Determination System to the new
TEDS Release 2. The processes
included identifying the gaps between current and future processes for
organizational alignment, staffing, training, processing, assets needed to
close the gaps, documentation, and communication.
While TE/GE
Division management improved their use of certain project management
techniques, they did not fully evaluate their investment decisions and did not
ensure alignment with the Enterprise Architecture. If prior Treasury Inspector General for Tax
Administration recommendations had been implemented, the cost overruns and
decrease in planned benefits may have been avoided or further minimized.
The cost of TEDS Release 2 may exceed the reduced monetary benefits delivered
TEDS Release 2 may be completed with significantly reduced
system capabilities and benefits. The
June 2004 TEDS Release 2 Business Case documented 16 high-level system
capabilities costing $46 million that would deliver benefits of $58 million. This Business Case was updated in August 2004
to document estimated benefits of $73.1 million. However,
after work began on Release 2, the TE/GE Division project team incurred delays
in delivering benefits (e.g., 4 system capabilities were deleted, some system
capabilities have been only partially delivered, and 5 system capabilities have
been delayed by up to 2 years). An
additional 8 capabilities were added, but the February 2007 TEDS Release 2
Business Case documents the System is now expected to deliver only $33.5
million (less than one-half) of the $73.1 million August 2004 expected
benefits.
TE/GE Division management advised us the August 2004 TEDS Release 2 Business Case benefits were recalculated in February 2007 to correct:
· Benefit projections that used double inflation for labor.
· Benefit projections for changes in scope, schedule, and other financial factors.
· Cyber Assistant application benefit projections.
In addition, according to TE/GE Division management, part of
the large decrease in benefits was due to the elimination of certain TEDS
features because functions that were intended to be performed by another system
could not be accomplished as planned. Figure 1 shows a comparison of the cost and
benefits calculations for the TEDS Release 2 Business Cases dated June 2004,
August 2004, and February 2007.
Figure
1: Comparison of TEDS Business Case
Changes in Costs and Benefits (in millions) Between June 2004 and February 2007
Figure 1 was removed due to its size. To see Figure 1, please go to the Adobe PDF
version of the report on the TIGTA Public Web Page.
The February 2007
Business Case shows a significant decrease in benefits from both the June 2004
and August 2004 Business Cases. TE/GE
Division management also advised us that updates to the benefits calculations
after February 2007 will now put the benefits at over $35 million.
The Clinger-Cohen
Act of 1996[15] requires Federal Government agencies to use
a disciplined capital and investment control process to manage information
technology investments. Agencies are
required to put their technology investment decisions in a true “business
context” and analyze investments for their return on investment. Annually, the Office of Management and Budget
publishes Circular A-11, Preparation,
Submission and Execution of the Budget, to assist Federal Government
agencies in complying with the Clinger-Cohen Act of 1996. Circular A-11 provides guidance on the
preparation of business cases for information technology systems.
In addition,
according to organizational policy, the IRS requires tracking,
monitoring, and evaluating of all project costs[16]
and expected benefits against the approved business case. Business
cases provide decision makers with benchmark information necessary to make
evaluations on a project’s costs and benefits and a basis for measuring whether
multimillion dollar investments make good business sense.
We performed
additional reviews of documentation to determine whether TEDS project management
and the TE/GE Division Investment Executive Steering Committee tracked,
monitored, and evaluated project costs as required. We determined the following:
·
Project management did not have information that
associated the value of expected benefits to specific system capabilities. For example, the updated expected benefits in
the February 2007 Business Case show Release 2 is now expected to deliver
benefits of only $33.5 million, a decrease of $39.6 million from the August
2004 Business Case projection. Through
our review of documentation and discussions with project management, we could
not identify the relationship between the system capabilities and the benefits
that make up the $39.6 million that have been deleted. However, at the end of our audit work,
TE/GE Division management provided some information related to the changes
in benefits. Information that relates
the value of benefits to any changes in system capabilities is critical for
evaluating whether a system should receive continued funding and development.
·
Because project management did not have this
information for Release 2, the Investment Executive Steering Committee did not
receive the critical periodic updates of cost and benefit information needed to
assess the impact that delayed or undelivered system capabilities had on
expected benefits.
· Review of the Investment Executive Steering Committee’s monthly meeting notes identified the Committee addressed issues that concerned specific system capabilities or funding for specific contracts. However, we did not find any documented discussion of the collective impact of schedule delays and the deletion of system capabilities on overall project benefits and actual project costs. When we discussed this with Committee members, they advised us that schedule delays and benefits were regularly discussed at meetings. However, we were not provided documentation showing these topics were discussed. The Commissioner, TE/GE Division (a key member of the Investment Executive Steering Committee), also advised us that, while he may not have known the exact dollar figure by which benefits were decreasing, he and the Committee members always knew what capabilities the IRS would be receiving and what capabilities the IRS would be losing when making decisions. He stated the decision‑making process may not have involved looking back at the August 2004 Business Case. In addition, despite not knowing the exact amount by which benefits were declining, TE/GE Division management may not have considered other alternatives because the system the TEDS is replacing, the Employee Plans/Exempt Organizations Determination System, is a failing and dying system.
IRS policy provides that business cases may be updated any time during system development,[17] at the discretion of the Investment Executive Steering Committee. Conditions that may trigger a revision to the business case include changing the scope of the project, increasing the cost of the project by more than 10 percent, or extending the targeted delivery dates by more than 10 percent of the estimate. Adverse changes in cost, schedule, and performance do not, by themselves, automatically require a business case revision. However, if changes in cost, schedule, or performance result in modified baseline information and/or increases greater than 10 percent, a revision to the business case and approval from the Investment Executive Steering Committee may be needed to proceed with development. The revisions are necessary to ensure the most accurate information is available for making investment decisions, monitoring the progress of the system’s development, and evaluating whether business benefits are actually realized.
The TEDS Business Case was last updated in February 2007. However, due to the change in the project’s scope and the reduction in benefits of approximately 54 percent, we believe the Business Case should have been updated sooner. We could not determine the reason for the February 2007 update because actual costs compared to estimated costs and the changes in capabilities and benefits were not tracked. In addition to the significant reduction in benefits, there was at least an 8-month delay in the Release 2 implementation. For the TEDS, the TE/GE Division Investment Executive Steering Committee had a responsibility to determine whether the Business Case needed to be revised or updated. Knowing that the benefits decreased significantly, but not requesting a revision to the Business Case prevented the Committee from having full knowledge of the significant decrease in the benefits that the TEDS would deliver compared to the original estimates in the approved Business Case. Significant deviations from the Business Case, such as cost overruns or decreased capabilities or benefits, should be discussed as soon as they are identified.
A process to track and monitor total project cost
was not implemented, and overruns occurred
Total project costs were not monitored and reported because TE/GE Division management did not have a process in place to appropriately evaluate investment decisions associated with the development of TEDS Release 2. None of the actual project costs to develop, implement, and evaluate Release 2 were tracked and monitored as required by IRS procedures. As a result, project management was not aware that actual contractor costs significantly exceeded the estimate in the August 2004 Business Case.
We reviewed the Project Manager’s records and calculated that contractor costs exceeded the estimate by at least $2.1 million (an increase from $8.1 million to $10.2 million, or 26 percent) for Fiscal Years 2004 through 2006. In addition, IRS internal labor costs estimated at $5.1 million were not tracked. This information should have been provided to the TE/GE Division Investment Executive Steering Committee so it would be aware of significant deviations from the project’s estimated costs and could determine whether the expected return on investment was being achieved. As a result, the Committee could not evaluate performance and determine if the project was being delivered within estimated costs.
TE/GE Division management implemented
procedures in response to a recommendation[18] we made as part of our review
of the TEDS Release 1. We recommended
adopting a business case model to include processes for tracking and monitoring
actual project costs. TE/GE Division
management implemented procedures to verify actual contractor costs weekly to
ensure the expenses were actually incurred.
However, the procedures did not include tracking, comparing, monitoring,
and evaluating contractor costs and IRS internal labor costs to estimates in
the approved TEDS Business Case.
In addition, the Project Manager
advised us the current IRS timekeeping system does not adequately support
tracking internal labor costs. Release 2
project management advised us Federal Government labor cost is tracked back to
the project as actual cost as accurately as possible, considering the
limitations of the timekeeping system.
This has been a longstanding weakness in other areas of the IRS, such as
in the Modernization and Information Technology Services organization that
recently corrected the problem.[19]
We determined there was $7.2 million
of potentially unreliable information in the TEDS August 2004
Business Case for Fiscal Years 2004 through 2006. This includes $2.1 million paid to
contractors that exceeded the estimated amount in the Business Case and
$5.1 million in estimated IRS internal labor cost not tracked.[20]
Management Action: Project management informed us the TE/GE Division
Business Systems Planning function has been working to improve the tracking of actual Federal Government costs back to
investments; however, additional process changes need to be made to facilitate
reporting.
Minimal benefits were realized from TEDS Release 1
The TE/GE Division
received very few benefits from the development of Release 1. Approximately $17 million was spent to
purchase the technical infrastructure, including computer hardware and the
development of computer code. Upon
completion, Release 1 was expected to reduce cycle time, processing time, and
processing costs, while implementing process improvements to enhance the
quality of determinations and the quality of service delivered to TE/GE
Division customers. The technical infrastructure,
including computer hardware and software, was designed to support Release 1 and
all future TEDS releases.
However, according to TE/GE Division
management, the initial infrastructure had to be replaced when it was completed
because it did not meet new IRS standards.
As a result, an inefficient use of resources occurred and the TE/GE
Division realized little benefit from its $17 million investment for
Release 1.[21]
Management
oversight may not ensure TEDS Release 2 will align with the future IRS
Enterprise Architecture
Project management oversight may not ensure Release 2 will align with the future Enterprise Architecture. Oversight is necessary to ensure additional costs are not incurred in the future to bring the applications into alignment with the Enterprise Architecture. We identified the following two documents were not completed or approved as required.
· The Release 2 Enterprise Architecture Assessment was not completed. This omission is significant because the purpose of the Assessment is to determine whether the project is consistent with the Enterprise Architecture to ensure computer systems designed and built separately will improve performance and productivity.
· The Enterprise Architecture Charter for Release 2 was incomplete and had not been approved. This Charter is used to manage the scope of the project in a manner that is consistent with the IRS Enterprise Architecture.
The development, modernization, and enhancement of projects, such as TEDS Release 2, must show compliance with the IRS Enterprise Architecture. Enterprise Architecture Directive 15, Project Chartering and Conformance with the IRS Enterprise Architecture, applies to all projects that are part of the future Architecture. Projects such as TEDS Release 2 require chartering and verification of conformance to the Enterprise Architecture.
Anticipated
benefits of Release 2, such as streamlined work processes and improved service
delivery and efficiency, may not be realized if management does not ensure
Release 2 is in alignment with the approved Enterprise Architecture.
Likewise, incomplete and unapproved project documentation increases the
risk that Release 2 will not be successfully integrated into the Enterprise
Architecture.
Recommendations
Recommendation 1: The Commissioner, TE/GE Division, should implement controls to ensure costs and the impact of schedule delays and changes in system capabilities on expected benefits are tracked. The TE/GE Division Investment Executive Steering Committee should review these impacts against business cases and ensure business cases are timely updated.
Management's Response: IRS management agreed with the recommendation. The TE/GE Division Business Systems Planning function governance and control office will implement controls to ensure costs and the impact of schedule delays and changes in system capabilities on expected benefits are tracked. The TE/GE Division Investment Executive Steering Committee will review these impacts against business cases and ensure business cases are timely updated. However, IRS management disagreed with our $17 million inefficient use of resources outcome measure representing the funds spent to purchase the technical infrastructure, including computer hardware and the development of computer code. The Office of Audit Comment in Appendix IV (page 19) describes in more detail management’s response and our position with respect to this outcome measure.
Recommendation 2: The Director,
Business Systems Planning, should complete plans to improve the tracking of
actual Federal Government costs back to investments and ensure this information
is provided periodically to the TE/GE Division Investment Executive Steering
Committee so it has complete information for evaluating system development
projects.
Management's Response: IRS management agreed with the recommendation. The Director, Business Systems Planning, will complete plans for improving the tracking of actual Federal Government costs back to investments and ensure this information is provided periodically to the TE/GE Division Investment Executive Steering Committee.
Appendix I
Detailed Objectives, Scope, and Methodology
The overall objectives of this review were to
determine whether the TE/GE Division developed TEDS
Release 2 using sound system development practices
and whether it managed the Release 2 investment in compliance with
Office of Management and Budget and Clinger-Cohen Act of 1996[22] requirements. To
accomplish these objectives, we:
I.
Determined if TE/GE Division management applied and
adhered to the approved Enterprise Life Cycle-Lite[23] methodology for
development of TEDS Release 2.
Specifically, we determined if:
A. TE/GE Division management’s development approach was adequate to monitor and control the Release 2 activities from project startup through closure.
B. The risk management process was adequate to identify, quantify, respond to, and control the risks that could prevent successful completion of the project.
C. The configuration management process was adequate to identify, document, monitor, evaluate, and approve all changes to system requirements.
D. The requirements management process adequately identified the Release 2 user requirements.
E. The transition management process was adequate to ensure Release 2 is ready for deployment and transfer to the Modernization and Information Technology Services organization.
II.
Determined if TE/GE Division management ensured
alignment with the IRS Enterprise Architecture.
Specifically, we determined if:
A. The Release 2 project team adhered to Enterprise Architecture requirements.
B. Project documents identified how Release 2 fits into the IRS architecture of the future.
C. The project team had coordinated its development efforts and resolved any differences with the Tier II Project Office.
III.
Determined if TE/GE Division management’s investment
decisions followed estimates in the TEDS Business Cases.
A. Compared the expected and actual Release 2 capabilities and determined if Release 2 was developed as intended to deliver the expected benefits.
B. Reviewed project management records and determined if actual expenditures were compared to estimates in the August 2004 Business Case.
C. Followed up on the development of Release 1 and determined whether benefits outlined in the August 2003 Release 1 Business Case were delivered.
Internal controls
methodology
Internal controls relate to management’s
plans, methods, and procedures used to meet their mission, goals, and
objectives. Internal controls include
the processes and procedures for planning, organizing, directing, and
controlling program operations. They
include the systems for measuring, reporting, and monitoring program
performance. We determined the following
internal controls were relevant to our audit objectives: Office of Management and Budget policies,
Clinger-Cohen Act of 1996 requirements,
Enterprise Life Cycle-Lite requirements, and IRS investment management
requirements. We reviewed these
controls by interviewing Business Systems Planning function and Exempt Organizations
function management, analyzing Investment Executive Steering Committee minutes,
and reviewing various project plans.
Appendix II
Major Contributors to This Report
Nancy A. Nakamura, Assistant Inspector General for Audit (Headquarters Operations and Exempt Organizations Programs)
Troy D. Paterson, Director
Gerald T. Hawkins, Acting Director
Julia M. Collins, Acting Audit Manager
John
W. Baxter, Lead Auditor
Andrew
J. Burns, Lead Auditor
Deadra
M. English, Senior Auditor
Yasmin
B. Ryan, Senior Auditor
Michael
A. McGovern, Auditor
Appendix III
Acting Commissioner C
Office of the Commissioner – Attn: Acting Chief of Staff C
Deputy Commissioner for Services and Enforcement SE
Deputy Commissioner, Tax Exempt and
Government Entities Division SE:T
Director,
Business Systems Planning, Tax Exempt and Government Entities Division SE:T:BSP
Director, Exempt Organizations, Tax Exempt and Government Entities Division SE:T:EO
Chief Counsel CC
National
Taxpayer Advocate TA
Director, Office of Legislative Affairs CL:LA
Director, Office of Program Evaluation and Risk Analysis RAS:O
Office of Internal Control OS:CFO:CPIC:IC
Audit Liaison: Director, Communications and Liaison, Tax Exempt and Government Entities Division SE:T:CL
Appendix IV
This appendix presents detailed information on the measurable impact that our recommended corrective actions will have on tax administration. These benefits will be incorporated into our Semiannual Report to Congress.
Type and Value of Outcome Measure:
· Reliability of Information – Potential; $39.6 million (see page 4).
Methodology Used to Measure the Reported Benefit:
IRS project management did not have information that associated the value of expected benefits to specific system capabilities. For example, the updated expected benefits in the February 2007 TEDS Business Case show Release 2 is now expected to deliver benefits of only $33.5 million, a decrease of $39.6 million from the original projection in the August 2004 TEDS Business Case. Information that relates the value of benefits to the system capabilities is needed to assess the impact that delayed or undelivered system capabilities had on the expected benefits of Release 2. Because this information was not available, project management could not assess the impact the decrease in expected benefits had on the Release 2 investment.
Benefits expected from Release 2 listed in the
August 2004 Business Case $73.1
million
Less: Benefits
expected from Release 2 listed in the
February 2007 Business Case $33.5
million
Total $39.6
million
Type and Value of Outcome Measure:
· Reliability of Information – Potential; $7.2 million (see page 4).
Methodology Used to Measure the Reported Benefit:
We determined contractor costs were
being tracked; however, the IRS did not compare actual contractor costs to the
estimated contractor costs listed in the August 2004 Business Case. We made this comparison and determined
contractor costs had exceeded estimates by $2.1 million through Fiscal Year 2006. We also determined TE/GE Division management
was not tracking internal labor costs; therefore, we could not determine
whether the $5.1 million estimated for IRS internal labor in the August 2004
Business Case was reliable. We added
these amounts to determine the amount of potential unreliable information in
the Business Case.
Amount contractor costs exceeded
estimates in the
August 2004 Business Case through Fiscal Year 2006 $2.1 million
Add:
Estimated IRS internal labor costs in the
August 2004 Business Case that were not tracked $5.1 million
Total of potentially unreliable cost information in the
Business Case $7.2
million
The estimated IRS internal labor
costs in the TEDS Business Case were taken directly from the August 2004
Business Case. The amount of contractor
costs that exceeded estimates in the TEDS Business Case through Fiscal Year
2006 were calculated by subtracting the estimated contractor cost to implement
Release 2 through Fiscal Year 2006 from the actual contractor cost to implement
Release 2 through Fiscal Year 2006.
Actual contractor cost to implement Release 2 through Fiscal Year 2006 $10.2 million
Less: Estimated contractor cost to implement
Release 2 through
Fiscal Year 2006 $8.1 million
Total by which contractor
costs exceeded estimates in the
August 2004 Business Case through Fiscal Year 2006 $2.1 million
We calculated the actual contractor
cost to implement Release 2 through Fiscal Year 2006 by adding contractor
invoice information collected by IRS project management. We calculated the estimated contract cost to
implement Release 2 through Fiscal Year 2006 by subtracting the estimated TE/GE
Division and IRS labor cost of $5.1 million listed in the August 2004 Business
Case from the $13.2 million total cost to implement Release 2 listed in that
Business Case.
Type and Value of Outcome Measure:
· Inefficient Use of Resources – Actual; $17.0 million (see page 4).
Methodology Used to Measure the Reported Benefit:
TEDS Release 1 did not significantly
improve the processing of Employee Plans function determination applications,
and the technical infrastructure designed to support future releases of the
System was replaced. As a result, the
TE/GE Division realized little benefit from its $17 million investment.
We determined the total Release 1
costs by adding prior project costs listed in the August 2003 TEDS Business
Case to IRS internal labor costs and contractor costs to complete Release 1.
Prior project costs listed in the August 2003 Business Case $12.0 million
Add: TE/GE Division internal labor costs from
August 7, 2003, through
February 17, 2006 $.5
million
Add: Contractor costs from August 7, 2003, through
February 17, 2006 $4.5 million
Total $17.0
million
The TE/GE Division labor costs to complete Release 1 were obtained from IRS project management. The contractor costs from August 7, 2003, through February 17, 2006, were calculated by adding contractor invoice information collected by IRS project management.
Office of Audit Comment
IRS management disagreed with 1 of the 3 outcome measures described in the report ($17.0 million in inefficient use of resources). The Commissioner, TE/GE Division, stated the lack of success in a venture such as TEDS Release 1 does not equate to inefficiency. Instead, lessons learned from Release 1 helped form new IRS standards in Enterprise Architecture that were used in TEDS Release 2 and will be used in all future IRS projects.
We agree that lessons learned did provide a benefit to the IRS; however, we believe there was little tangible benefit for the investment in TEDS Release 1. Furthermore, while we recognize the costs for TEDS Release 1 cannot be recovered at this point, increased controls over tracking costs, delays, or other system capabilities should help the IRS better monitor future projects and prevent implementation of new systems that are unable to accomplish their primary purposes.
In addition, the Commissioner, TE/GE Division, stated the TEDS project management team is working closely with the IRS Enterprise Architecture to comply with emerging standards as they apply to the TEDS and it is premature to conclude that Release 2 will not align with future Enterprise Architecture standards. We agree with the Commissioner’s conclusion and have made applicable wording changes to the report. However, we believe completing and approving required Enterprise Architecture documentation is a good preventive measure to ensure compliance with the future IRS Enterprise Architecture.
Appendix V
|
Term |
Definition |
|
Business Case |
Addresses how an investment project will provide the IRS with new
business capabilities, increased productivity, and improved management
decision-making tools. It provides a
basis for making investment decisions and establishes a project’s baseline
cost, schedule, and performance to control and evaluate the investment. |
|
Cyber Assistant |
An application that is an
interactive tool for exempt organizations that will provide real-time
education and guidance to assist in ensuring compliance with the tax law,
reducing customer burden, and increasing the
merit closure rates for Application for Recognition of Exemption Under
Section 501 (c)(3) of the Internal
Revenue Code (Form 1023). |
|
Cycle Time |
The period from when a
determination request is postmarked to the closing of the application and
issuance of the determination letter. |
|
Determination Letters |
Provide customers assurance
their employee plan or exempt organization is in compliance with applicable
tax laws. |
|
|
The IRS Enterprise
Architecture and its principles (1) provide the basis for defining
architectural strategies and making implementation choices and (2) help
business owners and program developers ensure proposed systems and other
initiatives are approved, resourced, and integrated into overall IRS computer
systems and processes. |
|
|
A disciplined system development methodology. |
|
Milestone |
A milestone represents the
completion of key activities within the project’s life cycle and is used to
measure progress and provide a review point for executive or oversight
approval. Projects must receive formal
approval to proceed from one milestone to the next. |
|
Requirements |
Generally, requirements reflect the needs of a user to solve a problem or achieve an objective. |
|
Restatement |
An application made to the IRS for an advance determination to ensure an amendment to an employee benefit plan meets the qualification requirements according to the Internal Revenue Code. |
|
Return on Investment |
The net profit or loss in
an accounting period divided by the capital investment used during the period,
usually expressed as an annual percentage return. |
|
Risk |
A potential event that, if
it occurs, will adversely affect the project’s cost, schedule, and/or
technical performance. |
|
Tier II |
Tier II refers to a tiered level of information technology equipment
(i.e., Tier I – Mainframes, Tier II – Servers, and Tier III – Desktops and
Laptops). |
Appendix VI
Management’s Response to the Draft Report
The response was
removed due to its size. To see the
response, please go to the Adobe PDF version of the report on the TIGTA Public
Web Page.
[1] In December 2001, the TE/GE Division Investment Executive Steering Committee approved a seven-stage release strategy for the TEDS to replace the Employee Plans/Exempt Organizations Determination System, automate certain manual processes, and reduce or eliminate employee labor expense. The System was needed to address several critical workload factors that threatened to overwhelm the Employee Plans function and Exempt Organizations function Determinations Programs.
[2] Federal Acquisition Reform Act of 1996 and Information Technology Management Reform Act of 1996, Pub. L. No. 104-106, 110 Stat. 642 (codified in scattered sections of 5 U.S.C., 5 U.S.C. app., 10 U.S.C., 15 U.S.C., 16 U.S.C., 18 U.S.C., 22 U.S.C., 28 U.S.C., 29 U.S.C., 31 U.S.C., 38 U.S.C., 40 U.S.C., 41 U.S.C., 42 U.S.C., 44 U.S.C., 49 U.S.C., 50 U.S.C.).
[3] The Tax Exempt Determination System Release 1 Delivered Only a Small Portion of the Expected Benefits and Significantly Exceeded Cost Estimates (Reference Number 2006-10-174, dated September 26, 2006).
[4] See Appendix V for a glossary of terms.
[5] See Appendix V for a glossary of terms.
[6] Executive-level members of the TE/GE Division Investment Executive Steering Committee are the Division’s Commissioner, Deputy Commissioner, and Directors and their Executive Assistants.
[7] The case grading system capability recommends the grade level of the employee assigned to work the case (i.e., General Service 9, 11, 12, or 13). The classification system capability shows the type of case to be worked (i.e., Automated, Merit, Non-Merit, and Washington Office).
[8] Application for Determination for Adopters of Master or Prototype or Volume Submitter Plans (Form 5307).
[9] The Tax Exempt Determination System Release 1 Delivered Only a Small Portion of the Expected Benefits and Significantly Exceeded Cost Estimates (Reference Number 2006-10-174, dated September 26, 2006).
[10] The Tax Exempt Determination System Release 1 Delivered Only a Small Portion of the Expected Benefits and Significantly Exceeded Cost Estimates (Reference Number 2006-10-174, dated September 26, 2006).
[11] See Appendix IV for further details.
[12] See Appendix IV for further details.
[13] See Appendix IV for further details.
[14] Project Management Techniques Need to Be Followed to Effectively Develop the Tax Exempt Determination System (Reference Number 2003-10-103, dated May 2003) and The Tax Exempt Determination System Release 1 Delivered Only a Small Portion of the Expected Benefits and Significantly Exceeded Cost Estimates (Reference Number 2006-10-174, dated September 26, 2006).
[15] Federal
Acquisition Reform Act of 1996 and Information Technology Management Reform Act
of 1996), Pub. L. No. 104-106, 110 Stat. 642 (codified in scattered sections of
5 U.S.C., 5 U.S.C. app., 10 U.S.C., 15 U.S.C., 16 U.S.C., 18 U.S.C., 22 U.S.C.,
28 U.S.C., 29 U.S.C., 31 U.S.C., 38 U.S.C., 40 U.S.C., 41 U.S.C., 42 U.S.C., 44
U.S.C., 49 U.S.C., 50 U.S.C.).
[16] Project costs include, but are not limited to, contract and Federal Government personnel direct and indirect labor costs that support the investment.
[17] IRS policy generally requires a business case to be updated after successful completion of integration, testing, acceptance, and piloting (testing the system in an actual business environment).
[18] The Tax Exempt Determination System Release 1 Delivered Only a Small Portion of the Expected Benefits and Significantly Exceeded Cost Estimates (Reference Number 2006-10-174, dated September 26, 2006).
[19] The Modernization and Information Technology Services Organization Can Improve Its Budget Formulation, Execution, and Review Processes (Reference Number 2007-20-064, dated May 9, 2007).
[20] See Appendix IV for further details.
[21] See Appendix IV for further details.
[22] Federal Acquisition Reform Act of 1996 and Information Technology Management Reform Act of 1996, Pub. L. No. 104-106, 110 Stat. 642 (codified in scattered sections of 5 U.S.C., 5 U.S.C. app., 10 U.S.C., 15 U.S.C., 16 U.S.C., 18 U.S.C., 22 U.S.C., 28 U.S.C., 29 U.S.C., 31 U.S.C., 38 U.S.C., 40 U.S.C., 41 U.S.C., 42 U.S.C., 44 U.S.C., 49 U.S.C., 50 U.S.C.).
[23] See Appendix V for a glossary of terms.