Treasury
Inspector General for Tax Administration
Office of Audit
MODERNIZATION PROGRAM UNCERTAINTIES ARE AFFECTING THE ACCOUNT
MANAGEMENT SERVICES PROJECT DEVELOPMENT
Issued
on June 9, 2009
Highlights
Highlights of
Report Number: 2009-20-071 to the
Internal Revenue Service Chief Technology Officer.
IMPACT ON TAXPAYERS
The Account Management Services
(AMS) system will provide Internal Revenue Service (IRS) employees with
immediate access to taxpayer account data and the ability to perform
instantaneous transaction processing and daily account settlement. IRS management needs to decide what future
project development plans will be followed and improve project funding
controls. Addressing these issues will
allow the AMS system to help meet the ongoing need to modernize tax
administration processes, applications, and technologies, and to enhance the
level of service provided to the nation’s taxpayers.
WHY TIGTA DID THE AUDIT
This
audit was initiated as part of our Fiscal Year 2009 Annual Audit Plan for
reviews of the IRS Modernization Program.
The overall objectives of this review were to determine whether the AMS
project management team is following established systems development processes
to ensure effective and efficient delivery of AMS Releases 1.3 and 2.1 and to
assess the adequacy of internal controls to ensure appropriate expenditure and
reporting of funds used to support AMS system release activities.
WHAT
TIGTA FOUND
Adequate
documentation was developed and maintained to meet Enterprise Life Cycle
requirements for deliverables and work products for the development and
deployment of AMS Releases 1.3 and 2.1.
The AMS project management team completed deployment of Release 1.3 on
February 20, 2009, and Release 2.1 is on track for its scheduled August 5, 2009,
delivery.
In
Calendar Year 2007, the IRS conducted an extensive technical analysis on the
future of the AMS system and decided to modernize and reuse the Integrated Data
Retrieval System, eliminating the need to develop many of the capabilities
originally planned for the AMS system.
Because
of the tentative plans about its future, IRS executives need to make several
strategic decisions that will affect the future of the AMS system. The longer these decisions are delayed, the
greater the risk of costly rework.
Although
contracted work for the AMS system was performance-based, timely finalized, and
monitored, the contract was not developed in a manner to appropriately control
spending across releases. Because of the
form of the contract and the absence of key internal controls over funding, the
AMS project management team experienced difficulty in managing project funding
for Releases 1.3, 2.1, 2.2, and 3.1.
They initially approved spreading infrastructure costs across multiple
releases because these costs do in fact benefit multiple releases. However, because some development work was
associated with project infrastructure, budget managers began to spend development
funds in the same way.
WHAT TIGTA RECOMMENDED
TIGTA
recommended that AMS project management activities follow the appropriate
governance process to redirect remaining AMS funding to complete Releases 1.3
and 2.1. To address the need to improve
controls over project funding, the Chief Technology Officer should direct
project management teams and contracting officers to propose modernization task
orders with the ability to readily account for system development activity
funding on a release basis. Actions
should be taken to reinforce existing governance procedures to executives and
managers about release-specific project funding. Training and desk procedures on the proper
use of release-specific project funding should be provided, including steps for
preparing, reviewing, and approving requisitions.
The
IRS agreed with our recommendations. The
Account Management Services project request to realign funds to complete
Releases 1.3 and 2.1 followed the governance process, received approval from
governance committees, and notified external stakeholders. The Modernization and Information Technology
Services organization is taking actions to manage contracts on a project
release basis and plans to reinforce existing governance procedures to ensure that this topic is
included as an agenda item for discussion at appropriate Executive Steering
Committee meetings. Further, formal desk
procedures, including the appropriate use of release-specific and milestone-specific
project funding, are under development.
READ THE
FULL REPORT
To view the report, including the scope, methodology, and full IRS response, go to: http://www.treas.gov/tigta/auditreports/2009reports/200920071fr.html.
Email Address: inquiries@tigta.treas.gov
Phone Number: 202-622-6500
Web Site:
http://www.tigta.gov