Contract Files Lacked Sufficient Information to Support Determinations of Present Responsibility
September 30, 2011
Reference
Number: 2011-10-095
This report has cleared the Treasury Inspector General for Tax Administration disclosure review process and information determined to be restricted from public release has been redacted from this document.
Phone
Number | 202-622-6500
Email Address | TIGTACommunications@tigta.treas.gov
Web Site |
http://www.tigta.gov
HIGHLIGHTS
CONTRACT FILES LACKED SUFFICIENT
INFORMATION TO SUPPORT DETERMINATIONS OF PRESENT RESPONSIBILITY
Highlights
Final
Report issued on September 30, 2011
Highlights of Reference Number: 2011-10-095 to the Internal Revenue Service Chief, Agency-Wide Shared Services.
IMPACT ON TAXPAYERS
As of May 31, 2011, the Internal Revenue Service (IRS) Office of
Procurement was responsible for administering 1,008 procurements with a
reported life-cycle value of approximately $39.2 billion. The IRS does not have an effective process to
ensure that contracting officers’ determinations of present responsibility are
adequately conducted and documented in compliance with Federal Acquisition
Regulation requirements. As a result, the
IRS has an increased risk that procurements may be awarded to nonresponsible contractors.
WHY TIGTA DID THE AUDIT
This audit was initiated because the Federal Acquisition
Regulation requires that Federal agencies award procurements only to
contractors that are presently responsible (i.e., reliable, dependable, and
capable of performing required work on time and in a satisfactory manner). The overall objective of this review was to
determine whether the IRS has an effective process for conducting and
documenting present responsibility determinations to ensure that dishonest,
unethical, or otherwise nonresponsible contractors are not awarded IRS procurements.
WHAT TIGTA FOUND
The IRS does not have an effective process to ensure
that contracting officers’ determinations of present responsibility are
adequately documented. Contract files
did not contain sufficient documentation to support IRS contracting officers’
affirmative determinations of contractors’ present responsibility in 60 (68 percent)
of 88 files reviewed. In addition,
managerial reviews of present responsibility determinations were either not conducted or did not address the missing documentation. As a
result, the IRS has an increased risk that procurements may be awarded to
nonresponsible contractors, potentially leading to additional costs to the
Federal Government due to subsequent default, late deliveries, or other
unsatisfactory contractual performance.
WHAT TIGTA RECOMMENDED
TIGTA
recommended that the Chief, Agency-Wide Shared Services: 1) develop and implement guidance clearly
indicating specific, minimally acceptable, required documentation for present
responsibility determinations, and establish a specific time period for
reviewing the Excluded Parties List System and the Central Contractor
Registration database; 2) provide training for contracting officers on properly
conducting and documenting present responsibility determinations; and 3) update
managerial review guidance to include review of the contracting officers’
present responsibility determinations.
IRS
officials agreed with the recommendations.
The IRS stated it issued new guidance which includes a requirement for
contracting officers to perform all required contractor qualification checks
and maintain documentation of these checks in the contract files. The IRS also conducted a “Lessons Learned” training
session in June 2011 on the new guidance.
Additionally, the IRS is updating managerial review guidance to include
more explicit contract file review requirements.
TIGTA
noted that the new guidance issued does not fully address all of the concerns
TIGTA identified. Additional guidance is
needed on how procurement staff should conduct responsibility determinations,
examples of appropriate documentation to be maintained for each of the criteria
and provisions of law that must be examined, and the specific time period for conducting
contractor qualification checks.
September 30, 2011
MEMORANDUM FOR CHIEF, AGENCY-WIDE SHARED SERVICES
FROM: Michael R. Phillips /s/ Michael R. Phillips
Deputy Inspector General for Audit
SUBJECT: Final Audit Report – Contract Files Lacked Sufficient Information to Support Determinations of Present Responsibility (Audit # 200910023)
This report presents the results of our review to determine whether the Internal Revenue Service has an effective process for conducting and documenting present responsibility determinations to ensure that dishonest, unethical, or otherwise nonresponsible contractors are not awarded Internal Revenue Service procurements. This review was included in our Fiscal Year 2009 Annual Audit Plan and addresses the major management challenge of Erroneous and Improper Payments.
Management’s complete response to the draft report is included as Appendix VII.
Copies of this report are also being sent to the Internal Revenue Service managers affected by the report recommendations. Please contact me at (202) 622-6510 if you have questions or Nancy A. Nakamura, Assistant Inspector General for Audit (Management Services and Exempt Organizations), at (202) 622-8500.
Appendices
Appendix
I – Detailed Objective, Scope, and Methodology
Appendix
II – Major Contributors to This Report
Appendix
III – Report Distribution List
Appendix
IV – Sources of Information for Present Responsibility Determinations
Appendix
V – Legal Provisions for Disqualification From or Ineligibility
for Awards
Appendix
VI – Glossary of Terms
Appendix
VII – Management’s Response to the Draft Report
Abbreviations
|
CCR |
Central Contractor Registration |
|
EPLS |
Excluded Parties List System |
|
FAPIIS |
Federal Awardee Performance and
Integrity Information System |
|
FAR |
Federal Acquisition Regulation |
|
GSA |
General Services Administration |
|
IRS |
Internal Revenue Service |
|
PPIRS |
Past Performance Integrated Retrieval
System |
As of May 31, 2011,
the Internal Revenue Service (IRS) Office of Procurement was responsible for
administering 1,008 procurements[1] – 807 contracts of varying types (including
associated task and delivery orders) and 201 in blanket purchase agreements and
interagency contracts and agreements. The
1,008 active procurements have a reported systems life value of approximately $39.2
billion.
While
the Federal Government seeks to procure goods and services at the lowest
possible cost, awarding a contract based on lowest price alone may not always
result in the best value to the Federal Government. Additional unforeseen and/or unplanned costs
may be incurred by the Government due to subsequent contract default, late
deliveries, or other unsatisfactory contractual performance when awards are
made to contractors who are not qualified (or “nonresponsible”)
to perform the work. Contracting officers make present responsibility
determinations, after considering whether prospective contractors meet certain
legal standards, and must use the policies, standards, and procedures
prescribed in the Federal Acquisition Regulation (FAR)[2] to make the determinations. They must consider whether prospective
contractors: 1) can be expected to
complete contract work on time and in a satisfactory manner, 2) are structured
in such a way that doing business with them promotes socioeconomic goals, and
3) meet statutory or regulatory requirements for eligibility. Currently, under the FAR, the Government relies
upon two primary means to avoid doing business with nonresponsible contractors:
present responsibility determinations
and exclusion (i.e., suspension and debarment).[3]
Contracting officers are required to determine
prospective contractors’ responsibility prior to each contract award by
considering information submitted by the contractor or information they research
or acquire from other sources. However, contracting
officers have substantial discretion as to the nature and quantity of
information considered in making present responsibility determinations.[4] Because of the potential for bid protest, it
is important that present responsibility determinations be thoroughly conducted
and well documented.
To be considered presently
responsible under the FAR, prospective contractors must meet general standards.
These standards include the following
seven criteria related to contractors’ capabilities and conduct:
1) Adequate financial resources.
2) Ability to comply with the delivery or
performance schedule.
3) Satisfactory performance record.
4) Satisfactory record of integrity and business
ethics.
5) Necessary organization and experience.
6) Necessary equipment and facilities.
7) Otherwise qualified and eligible.[5]
In addition to the general standards,
contractors may have to meet special standards which apply only to specific procurements.
Special standards must be explicitly
included in agencies’ solicitations. They
are used, for example, when unique expertise, special facilities, or specific
experience or equipment are necessary to ensure that the Federal Government’s
needs are met. These special standards
are also considered in the contracting officers’ present responsibility
determinations.
Agencies also use exclusion, collectively
known as suspension and debarment, to avoid doing business with nonresponsible
contractors. Decisions to exclude are
made by agency heads or their designees (above the contracting officer’s level)
based upon evidence that contractors have committed certain integrity offenses,
including any “offenses indicating a lack of business integrity or honesty that
seriously affect the present responsibility of a contractor.”[6] Exclusion
is Government-wide and not contract specific.
Contracting officers should first check the Excluded Parties List System (EPLS) to ensure that excluded contractors do not unintentionally receive new procurements during their period of exclusion (i.e., while the contractor is suspended, debarred, or proposed for debarment). The EPLS contains the names of companies or individuals excluded from Federal procurements or other Federal funding such as grants. The EPLS also includes an archive of “past exclusions” dating back to Calendar Year 1988. Past exclusions have no present impact on contractor eligibility, but provide information on whether the entity has engaged in repetitive inappropriate patterns of conduct, and may indicate an unsatisfactory record of integrity and business ethics.
The FAR also requires prospective Federal Government contractors to be registered in the Central Contractor Registration (CCR) database in order to be awarded procurements by the Federal Government. The CCR database is the primary contractor registration database for the Federal Government. The CCR database is a part of the Business Partner Network which collects, validates, stores, and disseminates data in support of agency acquisition missions, including Federal agency contract and assistance awards. In addition, contractors must report semiannually and maintain accurate information in the CCR on any occurrences such as criminal convictions, civil proceedings, and administrative proceedings.
This review was performed at the Office of Procurement in Oxon Hill, Maryland, and at the IRS regional Procurement Field Offices in Oakland, California; Atlanta, Georgia; New York, New York; and Dallas, Texas, during the period October 2009 through May 2011. The scope of this audit was focused on present responsibility determinations and did not include a review of any other preaward requirements, including tax checks.[7] We conducted this performance audit in accordance with generally accepted government auditing standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objective. We believe that the evidence obtained provides a reasonable basis for our findings and conclusions based on our audit objective. Detailed information on our audit objective, scope, and methodology is presented in Appendix I. Major contributors to the report are listed in Appendix II.
The IRS does not have an effective process to ensure that contracting officers’ determinations of present responsibility are adequately documented. As a result, we could not determine whether the determinations were conducted in compliance with FAR requirements or whether the IRS awarded the related procurements to only presently responsible contractors. We found that 60 (68 percent) of 88 contract files did not contain sufficient documentation to support IRS contracting officers’ determinations of contractors’ present responsibility. In addition, managerial reviews of present responsibility determinations were either not conducted or did not address the missing documentation supporting the present responsibility determinations. Where sufficient information was available in the contract files, we did not identify contractors that were nonresponsible. However, due to the lack of documentation, the IRS has an increased risk that procurements may have been awarded to nonresponsible contractors, potentially leading to additional costs to the Federal Government due to subsequent default, late deliveries, or other unsatisfactory contractual performance.
Contract Files Did Not Always Support Contracting Officers’ Affirmative Determinations of Present Responsibility
Contracting officers
must make an affirmative determination that a prospective contractor is
responsible prior to awarding the contract.
The contracting officer must also obtain sufficient information
to be satisfied that the prospective contractor meets the responsibility
requirements. When contracting officers lack sufficient information to determine that
the contractor is responsible, they must make a determination of
nonresponsibility.
The FAR also specifically requires that the contracting officer review the EPLS after the opening of bids or receipt of proposals and again “immediately prior to award” to ensure that no award is made to a contractor that is excluded (i.e., suspended, debarred, or proposed for debarment). In addition, upon the opening of bids or receipt of proposals, the FAR requires the contracting officer to verify the prospective contractor is registered in the CCR database.
The responsible contracting officer must establish a unique
contract file to house both required and supporting documentation from the
origination of the procurement through the life of the contract. This file serves as a background for informed
decisions at each step of the acquisition process, provides information for reviews
and investigations, and furnishes essential facts in the event of litigation (e.g.,
bid protest) or congressional inquiries. In addition, the Standards for Internal
Control in the Federal Government[8] requires clear documentation of all transactions and other significant
events, and that the documentation be readily
available for examination. Internal
control standards also require that qualified and continuous supervision
be provided to ensure that internal control objectives are achieved. While
IRS guidance states that procurement reviews will address legal, quality, and
regulatory compliance issues, the current guidance does not include specific
guidance on the review of present responsibility determinations.
We reviewed a sample of 88 contract files.[9] Our sample included the following types of procurements:
Contract files did not contain sufficient documentation to support IRS contracting officers’ affirmative determination of present responsibility in 60 (68 percent) of 88 files reviewed. The contract files did not document:[11]
Formal
contracts were not adequately documented for present responsibility determinations
Our review showed
that 13 (30 percent) of 44 formal contract files did not contain sufficient
support of the contracting officers’ evaluation of prospective contractors’
performance records, financial resources, and/or qualifications. The 13 formal contract files lacked documentation
of contractors’ past performance information from either the Past Performance
Integrated Retrieval System (PPIRS) and/or reference checks internal to the IRS,
or from other Federal agencies. Credit
reports and contractor professional qualifications were also not documented in 7
(54 percent) of the 13 contract files.
We reviewed the 13 formal contract files for evidence of managerial review and found that 6 (46 percent) of the 13 formal contract files were not reviewed. In the remaining seven, the contract files were reviewed, but we identified no review comments regarding the missing support for determinations of present responsibility.
The FAR provides a
list of sources for contracting officers’ use as a basis for documenting that FAR
standards have been met by the prospective contractor. However, contracting officers have broad discretion
in determining what specific documents from those sources provide the best
information to support their decision. See
Appendix IV for a list of the various sources of information that may be used to
determine present responsibility.
Although the IRS has
overall guidance for present responsibility determinations, the guidance does not
specify the documentation required to provide reasonable assurance that present
responsibility determinations were adequately conducted and documented. For example, IRS guidance for present responsibility
determinations includes a contract file content checklist that includes steps
requiring determinations of present responsibility; however, the checklist does
not indicate the specific documentation that should be reviewed and maintained
in the contract files. Finally, the IRS
did not provide any formal training for the proper conduct of present responsibility
determinations to ensure consistency and completeness. We believe that a lack of specific policy
guidance and training on how to properly conduct and document present
responsibility determinations contributed to the inconsistencies in conducting and
documenting the present responsibility determinations that we assessed. For example, discussions with 30 contracting officers
indicated that 19 (63 percent) did not regularly use database systems, such as the
PPIRS, which are readily available to them for obtaining information on
contractor past performance.
Contract files lacked documented
evaluations of contractors’ suspension or debarment status
Our review showed that 50 (57 percent) of 88 contract files did not support that the contracting officers reviewed the EPLS “immediately prior to award.” This included 26 of 44 formal contracts, 7 of 16 simplified acquisitions, and 17 of 28 GSA Schedule contracts. We identified instances where the contracting officers: 1) researched the EPLS, but the research was more than 15 calendar days prior to awarding the procurements (29 instances); 2) did not research the EPLS until after awarding the procurements (12 instances); or 3) did not research the EPLS at all (9 instances). When contracting officers do not research the EPLS immediately prior to awarding a procurement, there is an increased risk that procurements may be awarded during periods of contractor ineligibility. Our research of the EPLS for these 50 contractors did not identify any contractors that had been suspended, debarred, or proposed for debarment at the time the procurements were awarded.[13]
Neither the FAR nor IRS policy and procedures define a time period for “immediately prior to award.” We used 15 calendar days prior to the award date to evaluate whether IRS contracting officers reviewed the EPLS “immediately prior to award.” In practice, we believe that the review of the EPLS should occur as close as possible to the day the procurement is awarded to ensure the most current information is considered before awarding procurements. Because we could not readily determine when the opening of bids or receipt of proposals occurred, we focused our observations on the contracting officers’ research of the EPLS in relation to the procurement award date. The requirement for contracting officer review of the EPLS applied to all procurements included in our sample (i.e., formal contracts, simplified acquisitions, and GSA Schedule contracts) and should have been conducted for each of those procurements.
IRS procedures
include steps for reviewing the EPLS; however, the IRS indicated that the
requirement to review the EPLS “immediately prior to award” was often
overlooked. This may be due in part to
the lack of IRS guidance in defining a specific time period for compliance with
the FAR’s “immediately prior to award” requirement. Our discussions with contracting officers indicated
that they all were aware of the requirement to review the EPLS to ensure that
contractors were not currently suspended, debarred, or proposed for
debarment. However, IRS procurement policy
does not define the time period for this requirement. An IRS Office of Procurement Policy official stated
that the FAR does not define the word ‘immediately’ (used approximately 148
times and in many different contexts in the FAR) and, according to FAR
1.108(a), undefined words retain their common dictionary meaning.[14] Further,
in performing the EPLS reviews and other responsibilities, contracting officers
should be allowed wide latitude to exercise business judgment (FAR 1.602-2)
and must have the authority, to the maximum extent practicable and consistent
with the law, to determine the application of rules, regulations, and policies
on a specific procurement.
We believe that
defining the “immediately prior to award” time period is necessary to ensure
that the time between the contracting officer’s review of the EPLS and the awarding
of the procurement is minimal. In
addition, supporting documentation, such as a screen print of the portions of
the EPLS site that were examined and used as a basis for the determination,
should be maintained in the contract file to facilitate management reviews to
ensure that this step has been timely conducted.
Our analysis of contract file documentation showed that 65 (74 percent) of the 88 procurements had a documented EPLS review that was conducted prior to the procurement award. Figure 1 shows our analysis of the IRS’s research of the EPLS by the number of calendar days: 1) prior to awarding the procurements, 2) after awarding the procurements, or 3) not documented. Our analysis showed that, while 65 of 88 procurements had EPLS research conducted prior to the award, in only 36 instances (41 percent) was the research conducted within 15 calendar days of the procurement being awarded.
Figure 1: Analysis
of Documented IRS Research of EPLS
|
EPLS Research Conducted |
Number of Procurements |
Percentage of Total |
|
On or within 15 calendar days of procurement award: |
|
|
|
Day of award |
16 |
18% |
|
1 to 15 calendar
days prior to award |
20 |
23% |
|
Subtotal |
36 |
41% |
|
More
than 15 calendar days prior to procurement award: |
|
|
|
16 to 30 calendar days prior to award |
12 |
14% |
|
31 to 60 calendar days prior to award |
6 |
7% |
|
61 calendar days or more prior to award |
11 |
13% |
|
Subtotal |
29 |
33%[15] |
|
Total prior to procurement award |
65 |
74% |
|
Other observations: |
|
|
|
After procurement
award |
12 |
14% |
|
Not documented |
9 |
10% |
|
Date of
research could not be determined |
2 |
2% |
|
Subtotal |
23 |
26% |
|
Total |
88 |
100% |
Source:
Our analysis of 88 active contract files.
Contract files lacked documented evaluations of the central contractor
registration database
In 11 (18 percent) of the 60 contract files reviewed which required review of the CCR database (44 formal contracts and 16 simplified acquisitions), the documentation present in the file did not support that the contracting officer researched the CCR database prior to awarding the contract. Our research of the CCR database showed that all 11 contractors were registered at the time of our review (i.e., after award); however, we could not determine whether the contractors were registered at the time of contract award because we did not have access to historical CCR database information.
IRS management indicated that this occurred in most instances because the contracting officers relied on the interface between the IRS Integrated Procurement System and the CCR database that downloads information daily on registrants. They believe that the automated process in the Integrated Procurement System will identify a contractor who is not registered in the CCR database, and that this is sufficient to meet the requirements of the FAR. We do not believe that this process meets FAR requirements for ensuring the contractor is registered prior to the contract award.
When contracting officers
do not verify that the contractor is registered in the CCR database early in the
contractor selection process, rather than at the time of award, it increases
the risk that the resulting present responsibility determinations may not be
based on the appropriate contractor information (e.g., Data Universal Numbering
System number). In addition, because the contractor must maintain information on any
occurrences of criminal convictions, civil proceedings, and administrative
proceedings in the CCR database, the contracting
officer should review this information early in the selection process. Based on the
CCR review, if the prospective contractor provided information
indicating serious integrity and business concerns, the contractor could be
eliminated from the selection process, or the contracting officer may need to obtain
additional information during the present responsibility determination review to
make an affirmative determination.
IRS management indicated that they do not believe the FAR requires contracting officers to maintain documents supporting their responsibility determination in the contract file. They stated that it was sufficient if the contracting officer indicates that they completed this step on the current contract file content checklist and signed the procurement indicating responsibility was affirmed.
Procedures lack guidance
for managerial review of present responsibility determinations
IRS guidance[16] broadly states that Procurement Office
Directors are accountable for procurement quality and shall establish review
systems to ensure quality standards are maintained for all procurement actions within their offices,
including simplified acquisitions.
However, IRS procedures for review of individual procurement actions do
not specifically address the review of present responsibility determinations. In addition, our discussions with 11 managers
showed that the procurement office managers
had varying approaches for reviewing contract files and did not have a
consistent contract file review methodology.
This included the frequency of review and the status of the procurements
selected. For example, the frequency of
review varied from reviewing contract files prior to award, before closeout,
twice per year, or after the contract was awarded. Many of the managers also indicated they reviewed
a sample, rather than reviewing all contract files.
Without sufficient
documentation in the contract files and adequate review of present responsibility
determinations, IRS management cannot ensure that contracting officers
adequately perform determinations of responsibility and effectively ensure that
procurements are not awarded to excluded or ineligible contractors. As a result, the IRS has an increased risk
that procurements may be awarded to nonresponsible contractors. This could lead to additional costs to the
Federal Government due to contractor misconduct, integrity issues, subsequent
default, late deliveries, or other unsatisfactory contractual performance. In addition, determinations based on
inadequate information may disadvantage the prospective contractor or other
bidders, and could potentially increase the risk of a bid protest. We believe IRS management should review the
adequacy of the present responsibility determination as part of their contract
file review, whether before or after procurement award.
Changes implemented for present responsibility determinations
The Federal Awardee
Performance and Integrity Information System (FAPIIS) was developed and
implemented on April 22, 2010, to improve the Federal Government’s ability to
evaluate the business ethics and expected performance of prospective
contractors and grantees, and protect the Federal Government from doing
business with entities that are nonresponsible.
The FAPIIS is a distinct application accessed through the PPIRS and
available to Federal acquisition professionals for their use in award and
responsibility determinations. The FAPIIS
provides users access to integrity and performance information, proceedings
information from the CCR database, and suspension and debarment information
from the EPLS. As of April 2010, the FAR
requires contracting officers to review information on the FAPIIS, document
contract files for each contract to indicate how the information in the FAPIIS
was considered in any responsibility determination, and document actions taken
as a result of the information. When a
nonresponsibility determination is made, the contracting officer is required to
document that information in the FAPIIS.
Management Action: Toward
the end of our fieldwork, the IRS issued new guidance that includes:
While we did not
test these new processes and procedures, we believe that the guidance is an
improvement over the guidance that was in place at the time of our audit
testing. However, we noted that the guidance
does not fully address all of the concerns identified during our review. The guidance does not clearly define the
required range of supporting documentation[17] from the FAR-required sources that should be
included in the contract file. For
example, the policy guidance indicates “as applicable” but does not explain
what that means. The new guidance also indicates
that the FAPIIS report is to be included in the contract file, but the guidance
does not specify which FAPIIS reports the contracting officer should obtain. In addition, the guidance has not established
a time period for defining the EPLS check “immediately prior to award” and has
not established the required supporting documentation, such as a screen print,
for reviews of the EPLS and the CCR database.
Recommendations
The Chief, Agency-Wide Shared Service, should:
Recommendation 1: Develop and implement guidance for the proper conduct of present responsibility determinations. This guidance should:
Management’s
Response: The IRS agreed with
this recommendation. The new Procurement
Policy and Procedure Memorandum 9.1(A) includes an explicit requirement for
contracting officers to support their responsibility determinations by performing
all required contractor qualification checks as applicable, completing the
Determination of Responsibility form, and filing evidence of each required
contractor qualification check in the contract file as documentation. The IRS’s standard practice is to check
certain contractor qualifications after the receipt of the proposals and
immediately prior to contract award. The
IRS believes this to be an effective practice, and that, to date, the IRS has
never awarded a contract to a suspended or debarred contractor. The IRS believes defining a specific time period
for compliance with qualifications research does not allow the contracting
officers the latitude necessary to “exercise business judgment” and to
determine the application of rules and policies prescribed in the FAR.
Office
of Audit Comment: While the new Policy
and Procedure Memorandum 9.1(A), dated April 14, 2011, addresses some of our
requested corrective actions, it does not sufficiently address the following
aspects of our recommendation. This
guidance does not provide detailed instructions on how procurement staff should
conduct responsibility determinations (to include how the seven FAR criteria
and other provisions of law should be applied, the appropriate sources from
which to obtain contractor qualification documentation, and examples of
appropriate documentation to be maintained in the contract file for each of the
FAR criteria and provisions of law that must be examined prior to making a
responsibility determination).[18]
Additionally, we
believe it is important for the IRS to define the “immediately prior to award”
time period for performing the EPLS contractor qualification check. During our
review, we determined that this EPLS review occurred in many instances
significantly prior to procurement award.
For example, the EPLS review occurred more than 60 calendar days
prior to award in 11 of the 88 procurements we tested and was not performed
prior to award in 12 instances. We
believe this indicates a need for IRS management to clarify expectations of
when the EPLS “immediately prior to award” review
should be conducted. IRS management could establish a specific
time period which addresses the intent of “immediately prior to award” and
still allows some flexibility for contracting officer’s judgment.
Recommendation 2: Provide training for IRS contracting officers on the proper conduct and documentation of present responsibility determinations.
Management’s Response: The IRS agreed with this recommendation. The Office of Procurement Policy conducts
annual “Lessons Learned” training based on quality assurance review findings
and internal contract file auditing efforts.
The latest training, conducted in June 2011, included an emphasis on the
use of the required contract file checklists and included responsibility
determination documentation requirements implemented in the new Procurement
Policy and Procedure Memorandum.
Recommendation 3: Update guidance
for managerial review to include specific requirements for review of the contracting
officer’s detailed analysis and documented evaluation of present responsibility
determinations in the contract file.
Management’s Response: The IRS agreed with this recommendation. The IRS is updating the managerial review
guidance to add that each review shall confirm and ensure the proper file
organization and content (including the responsibility determination form with
supporting documentation attached), and solicitation and contractor/order
quality. The IRS also stated that two
separate “Lessons Learned” training sessions were conducted for managers to
emphasize key areas to review for compliance.
Appendix I
Detailed Objective, Scope, and Methodology
The overall objective of this review was to determine whether the IRS has an effective process for conducting and documenting present responsibility determinations to ensure that dishonest, unethical, or otherwise nonresponsible contractors are not awarded IRS procurements. To accomplish our objective, we:
I. Determined whether the IRS and the Department of the Treasury have established policies and procedures that comply with applicable authorities relating to the contracting officer’s determination of present responsibility, and how they ensure contractors that were suspended,[19] debarred, or proposed for debarment prior to award or option renewal, are prevented from being awarded additional Federal procurements.
A. Obtained, reviewed, and evaluated copies of the IRS’s and the Department of the Treasury’s written policies and procedures and documented practices used in determining when suspension and/or debarment of a contractor are in the Federal Government’s best interest.
B. Determined the current practices used to ensure that if contractors are suspended, debarred, or proposed for debarment immediately prior to award or option renewal, they are prevented from being awarded additional Federal procurements.
II. Determined whether the IRS effectively performs the contracting officers’ determinations of present responsibility as demonstrated by its ability to identify and exclude nonresponsible contractors from being awarded procurements.
A. Obtained a complete list of current contracting officers and a current list of active procurements.
B. Selected a judgmental sample of 30 contracting officers from a population of 130 IRS contracting officers as of September 2, 2009. We selected 7 of 87 contracting officers from the Office of Procurement in Oxon Hill, Maryland; 6 of 13 contracting officers from Oakland, California; 7 of 14 contracting officers from Dallas, Texas; 6 of 8 contracting officers from Atlanta, Georgia; and 4 of 8 contracting officers from New York, New York. The contracting officers selected at each location were those who administered/awarded procurements equal to or greater than $50,000. We used judgmental sample selection techniques to obtain representation of all the procurements the IRS Office of Procurement administers and to ensure coverage of the four regional IRS Procurement offices.
C. Interviewed contracting officers and obtained an understanding of their current practices in completing the determination of present responsibility under the FAR Part 9.[20]
D. Interviewed the sample contracting officers’ managers and determined the part they have in the present responsibility determination process.
E. Selected a judgmental sample of 88 active procurements. This included 74 procurements administered by the 30 contracting officers identified in Step II.B and 14 administered by or assigned to 8 contracting officers’ managers identified in Step II.D. The sample procurements had a total value of more than $142 million. The 38 contracting officers and supervisory contracting officers were assigned 365 active procurements totaling more than $361 million. We selected procurements equal to or greater than $50,000. The procurements were selected from IRS active procurements as of August 27, 2009, for Oakland, California; as of September 24, 2009, for Dallas, Texas; as of December 2, 2009, for Oxon Hill, Maryland, and Atlanta, Georgia; and as of January 25, 2010, for New York, New York. These dates were selected to correspond with our site visits to these locations.
1. Reviewed the contract files and determined whether the assessment of present responsibility was properly documented.
2. Determined whether the contracting officers reviewed the PPIRS for prior identified performance issues and documented that review in the contract file.
3. Determined whether the contracting officers contacted prior users (third-party sources) of the contractors, either internally at the IRS or externally from other Federal agencies, to obtain a reference on their past performance in terms of product or service quality, timely completion, and cost.
4. Determined whether the contracting officers reviewed the EPLS to determine whether the contractor and its subcontractors were currently suspended, debarred, or proposed for debarment.
5. Determined whether any of the contractors selected in our sample were listed on the EPLS. If any contractors selected in our sample appeared in the EPLS, we reviewed the contract award dates and determined whether they were suspended, debarred, or proposed for debarment at the time of award or option renewal.[21]
6. Determined whether the contracting officers reviewed the CCR database to ensure that the potential contractor was registered and eligible to be awarded a contract by the Federal Government.
Internal controls
methodology
Internal controls
relate to management’s plans, methods, and procedures used to meet their
mission, goals, and objectives. Internal
controls include the processes and procedures for planning, organizing,
directing, and controlling program operations.
They include the systems for measuring, reporting, and monitoring
program performance. We determined the
following internal controls were relevant to our audit objective: the FAR,[22] Department of the Treasury regulations, and IRS policies and procedures. We evaluated these controls by interviewing
management and contracting officers, reviewing applicable documentation, and
analyzing a judgmental sample of procurements.
Appendix II
Major Contributors to This Report
Nancy A. Nakamura, Assistant Inspector General for Audit (Management
Services and Exempt Organizations)
Alicia Mrozowski, Director
Darryl Roth, Audit Manager
Mildred Rita Woody, Audit Manager
Julia Moore, Acting Audit Manager
Melvin Lindsey, Lead Auditor
Ken Henderson, Senior Auditor
Trisa Brewer, Auditor
Appendix III
Commissioner C
Office of Commissioner – Attn: Chief of Staff C
Deputy Commissioner for Operations Support OS
Director, Procurement OS:A:P
Chief Counsel CC
National Taxpayer Advocate TA
Director, Office of Legislative Affairs CL:LA
Director, Office of Program Evaluation and Risk Analysis RAS:O
Office of Internal Control OS:CFO:CPIC:IC
Audit
Liaisons:
Deputy Commissioner for Operations Support OS
Chief, Agency Wide Shared Services OS:A
Director, Procurement OS:AP
Appendix IV
Sources of Information for Present
Responsibility Determinations
In making the determination of present responsibility, the contracting
officer shall consider relevant past performance information. The FAR[23] states that the contracting officer should use the
following sources of information to support present responsibility determinations:
·
Records and experience data, including
verifiable knowledge of personnel within the contracting office, audit offices,
contract administration offices, and other contracting offices.
·
The prospective contractor, including bid
or proposal information, questionnaire replies, financial data, information on
production equipment, and personnel information.
·
Commercial sources of supplier information
of a type offered to buyers in the private sector.
·
Preaward survey reports.[24]
·
Other sources such as publications;
suppliers, subcontractors, and customers of the prospective contractor;
financial institutions; Government agencies; and business and trade
associations.
Confidence in a
prospective contractor’s ability to perform satisfactorily or better is an
important factor in making a present responsibility determination decision. One method of gaining this confidence is the
evaluation of a prospective contractor’s performance on recently completed or
ongoing procurements for the same or similar goods or services. The
FAR stipulates that, “a prospective contractor that is or recently has been
seriously deficient in contract performance shall be presumed to be
nonresponsible, unless the contracting officer determines that the
circumstances were properly beyond the contractor’s control, or that the contractor
has taken appropriate corrective action.” Serious deficiencies in performance may
include delinquent performance, delivery of nonconforming items, failure to
adhere to contract specifications, late deliveries, poor management or technical
judgment, failure to correct production problems, failure to perform safely, and
inadequate supervision of subcontractors.
Contracting officers must consider the circumstances surrounding any
deficient performance when making present responsibility determinations, and
poor performance or default on one or several prior procurements is not, by
itself, sufficient grounds for disqualification.
Another important aspect of the FAR’s general
standards for present responsibility determinations is the evaluation of
integrity and business ethics. In
evaluating a contractor’s integrity and business ethics, contracting officers may consider
convictions or indictments of corporate officers, integrity offenses
constituting grounds for suspension under the FAR, repeated violations of State
law, or pending debarments. A lack of
integrity on the part of entities with which the contractor has close
relationships may also be considered. Because
contractors have an interest in being able to challenge allegations about their
integrity that could deprive them of their livelihood, due process is required
when a nonresponsibility determination is based on concerns about the
contractor’s integrity.
Sources of information to support present responsibility determinations
Based on our discussions with contracting officers and
evaluation of FAR requirements, the following are various sources of
information and the relation of the information to the present responsibility
determination requirements. The sources
of information include, but are not limited to:
·
Past performance information, such as from
the PPIRS, to evaluate whether or not the contractor has complied with prior
performance schedules,[25] the contractor’s overall past performance record,[26] and the contractor’s record of integrity or business
ethics.[27] When information is
not available, and/or when additional information on contractor performance is
needed for the present responsibility determination, the contracting officer
may conduct reference checks or preaward surveys of third-party sources.
·
Credit reports (e.g., Dun & Bradstreet
Comprehensive Report) or financial statements to evaluate whether the
contractor has the necessary financial[28] and technical[29] resources and the necessary organizational structure and
experience.[30]
·
Contractor qualifications or curriculum vitae from the contractor to evaluate technical skills, past
experience, and training.
·
The EPLS and the CCR database to evaluate
whether the contractor is otherwise qualified and eligible.[31] Among other
considerations, this includes determining whether the contractor has been suspended,
debarred, or proposed for debarment under the FAR, and is registered in the CCR
database. The cause and condition codes
in the EPLS may provide the provisions of law that were violated and/or any
other basis for exclusion or ineligibility.
Appendix V
Legal Provisions for
Disqualification From or Ineligibility for Awards
To be
determined responsible according to the FAR,[32] prospective contractors must otherwise be
qualified and eligible. This criterion
encompasses collateral requirements, or other provisions of law specifying when
contractors are disqualified from or ineligible for awards. Among other things, contractors are
disqualified or ineligible for awards if they: 1) do not comply with Federal Equal Employment
Opportunity requirements, 2) fail to agree to an acceptable plan for
subcontracting with small businesses, 3) are known Government employees, 4) are
quasi-military armed forces, or 5) have unavoidable and unmitigated
organizational conflicts of interest. The
following are the major collateral requirements when contractors are
disqualified from or ineligible for awards.
Figure 1: Major
Collateral Requirements[33]
|
Requirement |
Application |
|
Equal Employment
Opportunity (48 C.F.R. §
22.802(b); Exec. Order No. 11246, 30 Fed. Reg. 12319 (September 24, 1965) |
•
Contractors are ineligible
if they do not comply with the Equal Employment Opportunity requirements in
Executive Order 11246, which requires, among other things, that contractors
“take affirmative action to ensure that applicants are employed, and that
employees are treated during employment, without regard to their race,
color, religion, sex or national origin.” •
Contractors cannot
receive an award with an expected value of $10 million or more (excluding
construction contracts) unless the Office of Federal Contract Compliance
Programs at the Department of Labor determines in writing that the
contractor is compliant with Executive Order 11246. |
|
Requirement |
Application |
|
Small Business
Subcontracting Plans (15 USC §
637(d)(4)(C) (plans in negotiated procurements); |
•
Contractors are ineligible
if they fail to agree to an acceptable plan for subcontracting with small
businesses under the contract. Section
637(d) of the Small Business Act (15
U.S.C. § 637(d)) requires that all contracts with expected values of
more than $650,000 ($1.5 million in the case of construction contracts)
include a “subcontracting plan” that provides the “maximum practicable
opportunity” for various subcategories of small businesses to participate in
performing the contract. Plans must
include percentage goals for subcontracting with small businesses, veteran-owned
and service-disabled veteran-owned small businesses, HUBZone small
businesses, small disadvantaged businesses, and women-owned small
businesses. Plans must also describe
the steps that contractors will take to ensure that small businesses have an
equitable opportunity to compete for subcontracts. |
|
Government
Employees (48 C.F.R. §§
3.601-602) |
• Agencies may not knowingly award contracts to Government employees
or entities owned, or substantially owned or controlled, by Government employees. •
Contracting with Government
employees is permitted under certain narrow exceptions, such as when the Government’s
needs cannot otherwise be met. •
If a contracting officer
unknowingly contracts with a Government employee, the award generally will
not be disturbed unless there appears to have been favoritism or other
impropriety. |
Quasi-Military Armed
Forces (5 U.S.C. § 3108;
48 C.F.R.§ 37.109) |
• Agencies may not contract with the Pinkerton Detective
Agency or “similar organizations.” •
Prohibition applies
“only to contracts with organizations that offer |
|
Organizational
Conflicts of Interest (48 C.F.R. §§
9.500-9.508) |
• Agencies may not award contracts where there are organizational
conflicts of interest that cannot be avoided or mitigated. Disqualifying organizational conflicts of
interest could arise if a prospective contractor provided systems
engineering and technical direction, prepared specifications or work
statements, provided evaluation services, or obtained access to other
contractors’ proprietary information while performing other Government contracts. •
Possibility of an organizational
conflict of interest is not, in itself, grounds for disqualification. Rather, when contracting officers identify
an organizational conflict of interest, they must notify the contractor and
allow the contractor a reasonable opportunity to respond. •
Contracting officers have substantial discretion in determining
whether organizational conflicts of interest exist, and their determinations
will generally be reversed, if protested, only when they are clearly
unreasonable or directly contrary to statute or regulation. |
Appendix VI
|
Term
|
Definition
|
|
Affirmative Determination |
Affirmative is defined as “a statement of
agreement with an assertion or request.” In this instance, it is a positive
determination of responsibility for the prospective contractor. |
|
Bid Protest |
A bid protest is a dispute about contracts that
have been, or are about to be, awarded. Persons and companies may file a bid protest
with the Government Accountability Office, and the Government Accountability
Office will issue a decision on whether the Federal agency issuing the
contract has complied with Federal procurement laws and regulations. |
|
Bidder |
Any entity that is responding to or has responded
to a solicitation, including an offeror under a negotiated acquisition. |
|
Business Partner Network |
The single source for vendor data for the Federal
Government. The Business Partner
Network is a search mechanism that provides unprecedented views into several
key databases across Federal agencies. |
|
Central Contract Registration (CCR) |
The primary contractor registration database for
the Federal Government. The database
is used to collect, validate, store, and disseminate data in support of
agency acquisition missions, including Federal agency contract and assistance
awards. The required information
includes the contractor’s legal business name, address, and Data Universal Numbering System number (the
nine-digit number assigned by Dun & Bradstreet, Inc. to identify unique
business entities). Certain
contractors are exempt from the registration requirement, including classified
contracts and contracts to support unusual or compelling needs.[34] |
|
Certificate of Competency |
Document issued by a designated authority that the
named contractor has fulfilled the requirements of receiving and performing a
particular contract. |
|
Credit Report |
A record of an individual’s or company’s past
borrowing and payment history, including information about late payments and bankruptcy. |
|
Curriculum Vitae |
A comprehensive list of professional history
including terms of employment, academic credentials, publications, contributions,
or significant achievements. |
|
Data Universal
Numbering System Number |
The nine-digit number assigned by Dun & Bradstreet
to identify unique business entities. |
|
Debarment |
An action taken by a designated agency official to
exclude a contractor from Government contracting and |
|
Due Process |
No person can be subject to an individualized
proceeding in which he or she stands to lose one of the protected interests (in
the context of administrative law, either property or liberty) without
sufficient procedures to ensure that the Governmental action is fundamentally
fair. |
|
Dun & Bradstreet Comprehensive Report |
A commercial source of credit report information
providing insight on businesses, including financial stability. |
|
Excluded Parties List System (EPLS) |
A web-based system maintained by the GSA that
includes information regarding entities suspended, debarred, proposed for
debarment, excluded, or disqualified under the nonprocurement common rule, or
otherwise declared ineligible from receiving Federal contracts, certain
subcontracts, and certain Federal assistance and benefits. |
|
Financial Statements |
Written reports that quantitatively describe the
financial health of a company. These include
an income statement and a balance sheet, and often also include a cash flow
statement. Financial statements are
usually compiled on a quarterly and annual basis. |
|
Formal Contracts |
Open market acquisitions with award amounts of more
than the simplified acquisition threshold. |
|
General Services Administration (GSA) Schedule |
GSA Schedules are also referred to as Multiple
Award Schedules and Federal Supply Schedules. Under the GSA Schedules program, GSA
establishes long-term, Government-wide contracts with commercial firms to
provide access to millions of commercial supplies (products) and services at
volume discounts. |
|
Option Renewal |
Exercising the right in a contract by which, for a
specified time, the Government may elect to purchase additional supplies or
services called for by the contract, or may elect to extend the term of the
contract. |
|
Past Performance
Information Retrieval System (PPIRS) |
A web-enabled, Enterprise
application that provides timely and pertinent contractor past performance
information for the Department of Defense and the Federal acquisition
community for use in making source selection decisions. |
|
Preaward Survey Reports |
An evaluation of a prospective contractor’s
ability to perform a proposed contract. |
|
Simplified Acquisitions |
The acquisition of supplies and services,
including construction, research and development, and commercial items, the
aggregate amount of which does not exceed the simplified acquisition
threshold. The simplified acquisitions
threshold at the time of our review was $100,000; however, effective October
1, 2010, it was raised to $150,000. |
|
Socioeconomic Goals |
It is the policy of the United States, as stated
in the Small Business Act (15 U.S.C. § 631), that all small businesses have
the maximum practicable opportunity to participate in providing goods and
services to the Government. To ensure
that small businesses get their fair share, the Small Business Administration
negotiates annual procurement preference goals with each Federal agency and
reviews each agency’s results. |
|
Solicitation |
A request to submit offers or quotations to the
Federal Government. Solicitations
under sealed bid procedures are called “invitations for bids.” Solicitations under negotiated procedures
are called “requests for proposals.” Solicitations
under simplified acquisition procedures may require submission of either a
quotation or an offer. |
|
Suspension |
A temporary exclusion of a party pending the
completion of an investigation for debarment.
A contractor that is under a formal investigation is suspended. |
Appendix VII
Management’s Response to the Draft Report
DEPARTMENT OF THE TREASURY
INTERNAL
REVENUE SERVICE
WASHINGTON,
D.C. 20224
CHIEF
AGENCY-WIDE
SHARED SERVICES
August 29, 2011
MEMORANDUM
FOR MICHAEL R. PHILLIPS
DEPUTY INSPECTOR GENERAL FOR AUDIT
From: David A Grant /s/ David A. Grant
Chief, Agency-Wide Shared Services
Subject: Draft Audit Report -
Contract Files Lacked Sufficient Information to Support Documentation of
Present Responsibility (Audit #200910023)
Thank you for
the opportunity to respond to the subject audit report. This audit was conducted
to determine whether the IRS has established pre-award policies and procedures
that are in compliance with applicable authorities as they relate to the Contracting
Officers' (COs') determination of present responsibility, especially as it relates
to suspension and debarment. The Treasury Inspector General for Tax Administration
(TIGTA) also sought to determine if the IRS effectively performs the COs' determination
of present responsibility as demonstrated by its ability to identify and exclude
non-responsible contractors from being awarded contracts. Our response is attached.
TIGTA's
review resulted in a finding that the IRS does not have an effective process to
ensure that COs' determinations of present responsibility are adequately
documented. We agree with TIGTA's recommendations, as they will provide
consistency in the responsibility determination process. However, we feel it is
important to emphasize that TIGTA did not identify any contracts awarded to
suspended or debarred contractors, nor did they find that CO file documentation
practices violated the Federal Acquisition Regulation (FAR) or the Agency's
procurement policy.
CO
responsibility determination deficiencies exist only to the extent that Federal
law, the FAR, or the Agency's procurement policy was not followed. For example,
there is no FAR requirement to include copies of the Excluded Parties List
System (EPLS) review results in the contract file when the contractor in
question is not listed - only that the CO review the list twice. There is also
no FAR requirement to include a copy of the Central Contractor Registration
(CCR) review results in the contract file - only that the CO verify contractor
registration; therefore, no responsibility determination deficiency exists merely
because EPLS and CCR reviews were not documented in the contract file.
However, our
file content checklists, maintained in Policy and Procedures 4.1, File Content
Checklist, require verification of EPLS and CCR prior to contract award. This provision,
in accordance with the FAR, states that the "contracting officer's signing
of a contract constitutes a determination that the prospective contractor is
responsible with respect to that contract" (FAR 9.1 05-2(a) (1)).
We appreciate
the continued support and the valuable assistance and guidance that your team
provides. If you have any questions, please contact me or a member of your staff
may contact Barry Kearns, Director, Office of Procurement Policy, at (202)
283-1410. For matters concerning follow-up, please contact Larry Pugh, Office
of Strategy and Finance, Agency-Wide Shared Services, at (202) 622-4541.
Attachment
RECOMMENDATION
#1: Develop and implement guidance for the proper
conduct of present responsibility determinations. This guidance should:
CORRECTIVE
ACTION: We agree with this recommendation. The new
P&P 9.1 (A), Federal Awardee Performance and
Integrity Information System (FAPIIS), includes an explicit requirement for COs
to support their responsibility determinations by performing all required
contractor qualification checks (Dun & Bradstreet, Past Performance, CCR, two
EPLS, and Tax Checks as applicable), completing the Determination of Responsibility
form linked within P&P 9.1 (A), and filing evidence of each required contractor
qualification check in the contract file as documentation.
In regard to
defining a specific time period for compliance with EPLS research or CCR database
research, our standard practice, as defined in P&P 9.1 (A), is to check
certain contractor qualifications after receipt of proposals and immediately
prior to contract award. We feel this is an effective practice and, to date, we
have never awarded a contract to a suspended or debarred contractor. We feel
that defining a specific time frame for compliance with qualifications research
does not allow contracting officers the latitude necessary to "exercise
business judgment", and to determine the application of rules and
policies, as prescribed in FAR 1.602-2.
IMPLEMENTATION
DATE: Completed April 14, 2011
RESPONSIBLE
OFFICIAL: Director, Procurement, Agency-Wide Shared
Services (OS:A:P).
CORRECTIVE
ACTION MONITORING PLAN:
N/A
RECOMMENDATION
#2: Provide training for IRS contracting officers
on the proper conduct and documentation of present responsibility
determinations.
CORRECTIVE
ACTION: We agree with this recommendation. The Office
of Procurement Policy conducts annual "Lessons Learned" training
throughout Procurement based on quality assurance review findings and internal
contract file auditing efforts. This included an emphasis on the use of the
required contract file checklists, specifically, the lists included in P&P
Memorandum 4.1, File Content Checklists. P&P 4.1 provides a structured
approach to ensure Contracting Officers (COs) uniformly comply with the
responsibility determination requirement. An updated "Lessons
Learned" training was conducted in June 2011 and included responsibility
determination documentation requirements implemented in the new P&P 9.1(A).
IMPLEMENTATION
DATE: Completed July 20, 2011
RESPONSIBLE
OFFICIAL: Director, Procurement, Agency-Wide Shared
Services (OS:A:P).
CORRECTIVE
ACTION MONITORING PLAN:
N/A
RECOMMENDATION
#3: Update guidance for managerial review to
include specific requirements for review of the contracting officer's detailed
analysis and documented evaluation of present responsibility determinations in
the contract file.
CORRECTIVE
ACTION: We agree with this recommendation. We are
also updating managerial review guidance to add the following or more explicit
review requirements to P&P 4.1(B) at 4.1(B)(5)(b)(1)
under Internal Reviews:
"Each review shall confirm
and ensure the following: (1) proper file organization and content (signed
P&P 9.1 (A) responsibility determination form with supporting documentation
attached, as well as all other documentation required by the checklist), and
(2) solicitation and contract/order quality (evaluation criteria in both
technical evaluation plan and solicitation are identical, etc.)."
The Office of
Procurement Policy conducted "Lessons Learned" training throughout Procurement
last year, based on quality assurance review findings and internal contract file
auditing efforts, which included an emphasis on the use of the required
contract file checklists. Two separate "Lessons Learned" training
sessions were also conducted for managers who reviewed contract files to
emphasize key areas to review for compliance. Future contract file review
workshops will continue to include manager oversight reviews responsibilities.
IMPLEMENTATION
DATE: December 31, 2011
RESPONSIBLE
OFFICIAL: Director, Procurement, Agency-Wide Shared
Services (OS:A:P).
CORRECTIVE
ACTION MONITORING PLAN:
Corrective Actions will be
monitored in the JAMES system until complete.
[1] We broadly use the term procurements throughout this report to include contracts, task or delivery orders off of existing contracts, General Services Administration Schedule contracts, and simplified acquisitions.
[2] 48 C.F.R. ch. 1 (2009).
[3] Responsibility Determinations Under the Federal Acquisition Regulation: Legal Standards and Procedures, (Congressional Research Service, by Kate M. Manuel, Legislative Attorney, Reference Number R40633, dated October 1, 2010).
[4] See Appendix IV for a list of the various types of information that may be used in the contracting officers’ determination of present responsibility.
[5] This criterion includes other provisions of law specifying when contractors are disqualified from or are ineligible for awards. See Appendix V for a list of the provisions.
[6] Grounds for debarment include, among other things, convictions or civil judgments involving fraud or criminal offenses in connection with obtaining or performing a Government contract; violations of Federal or State antitrust laws relating to the submission of offers; embezzlement, theft, forgery, or similar offenses; and intentional misuse of the “Made in America” designation.
[7] Policy and Procedures Memorandum No. 9.1 (dated January 1, 2008) provides that IRS employees will complete a tax check on prospective contractors for all IRS solicitations more than $250,000, except for orders made under existing contracts awarded by other agencies, including General Services Administration Federal Supply Schedule contracts. For more information on tax checks see Treasury Inspector General for Tax Administration report Federal Guidelines Do Not Prohibit the Awarding of Contracts to Contractors With Delinquent Tax Liabilities (Reference Number 2010-30-120, dated September 28, 2010).
[8] GAO/AIMD-00-21.3.1, dated November 1999.
[9] See Appendix I for details of the sample selection.
[10] See Appendix IV for additional information on sources of information to support present responsibility determinations.
[11] The counts do not total 60 because we identified formal contracts and simplified acquisitions that had more than one type of information missing.
[12] The requirement for contracting officer review of the EPLS “immediately prior to award” applied to all contracts included in our sample (i.e., formal contracts, simplified acquisitions, and GSA Schedule contracts).
[13] Our research included reviewing the EPLS archive for contractors who were suspended or debarred. The archive includes historical information of “past exclusions” dating back to Calendar Year 1988.
[14] Dictionary.com defines “immediately” as without lapse of time, without delay, instantly, or at once.
[15] Percentage does not total 33 percent due to rounding.
[16] Policy and Procedures Memorandum No.4.1 (B), dated January 1, 2010.
[17] The current guidance does not specify the documentation that must be included in the contract file (e.g., screen print of the EPLS).
[18] The FAR Part 9 requires that documents and reports supporting a determination of responsibility or nonresponsibility, including any preaward survey reports, the use of FAPIIS information, and any applicable Certificate of Competency, must be included in the contract file.
[19] See Appendix VI for a glossary of terms.
[20] 48 C.F.R. ch. 1 (2009).
[21] Our evaluation of the EPLS for our sample contracts did not identify any contractors that were listed as currently suspended or debarred on the EPLS.
[22] 48 C.F.R. ch. 1 (2009).
[23] 48 C.F.R. ch. 1 (2009).
[24] See Appendix VI for a glossary of terms.
[25] FAR Part 9 requires that the contractor must be able to comply with the delivery or performance schedule.
[26] FAR Part 9 requires that the contractor must have a satisfactory performance record.
[27] FAR Part 9 requires that the contractor must have a satisfactory record of integrity and business ethics.
In evaluating the criterion for integrity and business ethics, contracting officers may consider convictions or indictments of corporate officers, integrity offenses constituting grounds for suspension under the FAR, repeated violations of State law, or pending debarments. The evaluation of this requirement may also include research of the EPLS and the CCR database.
[28] The FAR Part 9 requires that the contractor must have adequate financial resources.
[29] The FAR Part 9 requires that the contractor must have the necessary organization, experience, accounting and operational controls, and technical skills.
[30] The FAR Part 9 requires that the contractor must have the necessary production, construction, and technical equipment and facilities to perform the work required.
[31] The FAR Part 9 requires that the contractor must be otherwise qualified and eligible. See Appendix V for a list of the provisions of law specifying when contractors are disqualified from or ineligible for awards.
[32] 48 C.F.R. ch. 1 (2009).
[33] Responsibility Determinations Under the Federal Acquisition Regulation: Legal Standards and Procedures, (Congressional Research Service, by Kate M. Manuel, Legislative Attorney, Reference Number R40633, dated October 1, 2010).
[34] See the FAR Part 4 for a complete listing of the contractors exempt from the CCR database registration requirement.