Evaluation of the Service’s Efforts
To Acquire a New FFRDc
Reference No. 091502 Date: November 20, 1998
Table of contents
The Service has undertaken a complete redesign and modernization of its computer-based information processing system. To assist with the modernization efforts, the Service is soliciting a PRIME contractor and another Federally Funded Research and Development center (FFRDc) contractor to manage the overall modernization efforts. By establishing a FFRDc, the Service can obtain technical assistance without any organizational conflicts of interest, real or apparent.
The PRIME contract and the new FFRDc contract will be used in conjunction with several other contracts to implement the planned modernization. The PRIME contractor will implement the modernization blueprint, and the new FFRDc contractor will validate the approach of the PRIME contractor to ensure it is consistent with the modernization blueprint.
The overall objective of this review was to assess the effectiveness of the solicitation process. Audit work was performed during the period of January 1998 through June 1998 in the National Office.
Results
Although the Service is soliciting contractors to assist with its modernization efforts, we determined additional emphasis is needed to define the interrelated roles of the various contractors and ensure all contractors remain free from potential conflicts of interest.
Management needs to clearly define the responsibilities of all contractors involved in the modernization efforts.
The roles and responsibilities of the major contractors contributing to the modernization efforts have not been fully defined. Management’s indecision on contractor responsibilities resulted in changes to the new FFRDc solicitation and delayed contract award 18 months from the original target date.
The delays have impacted the initial purpose of the new FFRDc contract. Originally, the new FFRDc was to be involved in the PRIME solicitation. However, due to the delays in awarding the new FFRDc contract, the solicitation was amended to remove all references to the PRIME solicitation. Without identifying each contractor’s role in the effort, the Service is at risk of duplicating efforts, incurring additional costs, not receiving its anticipated outcomes, and delaying the modernization efforts.
Procurement personnel need to take additional pro-active steps to ensure the FFRDc will be free from organizational conflicts of interest.
Procurement officials do not have sufficient measures for ensuring the FFRDc remains free from organizational conflicts of interest. currently, the FFRDc contractor signs a statement agreeing to maintain its objectivity and independence. However, Procurement does not validate the contractor’s compliance with this statement.
Although the selected contractor’s policy and procedures will be incorporated into the contract, this does not ensure freedom from organizational conflicts of interest. We believe a periodic validation of the FFRDc’s compliance with its internal policies and procedures needs to be implemented. The need for the FFRDc contractor to be impartial is vital because during the 15-year life of the multi-billion dollar PRIME contract, the FFRDc contractor will be evaluating the PRIME’s performance and providing recommendations. If the FFRDc is not free from conflicts of interest, the Service cannot rely upon the evaluations and recommendations provided by the FFRDc.
Summary Recommendations
The following summarizes the specific recommendations contained in this report:
The overall objective of this review was to assess the effectiveness of the solicitation process. Audit work was performed during the period of January 1998 through June 1998 in the National Office. The review was conducted in accordance with generally accepted government auditing standards. The detailed scope and objectives of the review are presented in Attachment I.
The Service has undertaken a complete redesign and modernization of its computer-based information processing system. To assist in the modernization efforts, the Service established the following contracts: Integrated Support contract (ISc), Treasury Information Processing Support Services (TIPSS), and a Federally Funded Research and Development center (FFRDc) contract with the Illinois Institute of Technology and Research Institute (IITRI). In addition to these contracts, the Service is soliciting a PRIME contractor and another FFRDc to manage the overall modernization efforts.
The framework for the modernization efforts was outlined by the ISc contractor in a "modernization blueprint". The Service is in the process of selecting a PRIME contractor to implement the modernization blueprint, and a new FFRDc contractor to validate the approach of the PRIME contractor to ensure it is consistent with the modernization blueprint.
The General Accounting Office and congressional review have determined, and the Department of Treasury and the Modernization Management Board have acknowledged, that there is a critical need for strategic information management. By establishing a FFRDc, technical assistance can be obtained without any organizational conflicts of interest, real or apparent. The nature of a FFRDc lends itself to a cost-effective, responsive, long-term relationship and allows the use of private sector resources to accomplish tasks that are integral to the mission of the agency.
The Service recognized the critical need for an objective source of expert advice and guidance in determining, planning and evaluating the management and oversight of the modernization efforts. With multiple contractors to assist the Service in its modernization efforts, the Acting Associate commissioner for Modernization/ chief Information Officer (cIO) was seeking to identify the appropriate roles for all the contractors. On June 11, 1998, the Acting cIO held a meeting with Information Systems and Procurement personnel to discuss the appropriate usage of the various contracts. However, we were advised that a decision was not reached during the meeting.
While the Service recognized its need for the technical expertise of a FFRDc contractor, the 18-month delay in contract award has altered the intended use of this contract. During our review, we determined that improvements are needed in awarding and monitoring the FFRDc contract. Specifically, we noted:
The Service has not timely awarded the new FFRDc contract because management was indecisive about the roles and responsibilities of the major contractors contributing to the modernization efforts. As a result of the delays, the FFRDc contract will not be used for its original intended purpose.
Information Systems determined that a new FFRDc contract was needed in October 1996 and requested Procurement’s assistance. The Service used the streamlined procurement process, and anticipated contract award in March 1997. currently the solicitation is in Phase III, contractors’ oral presentations and negotiations. A firm contract award date has not been established; however, Procurement personnel anticipate awarding the new FFRDc contract in September 1998.
Due to the significant delay in awarding the new FFRDc contract, the tasks outlined in the original Request for Proposal (RFP) cannot be performed. For example, the original RFP required the FFRDc contractor to assist in preparation of the PRIME RFP and assist with the PRIME bid evaluation. The Service has already issued the final PRIME RFP and bids were received June 1, 1998. The PRIME bids are currently being evaluated. Therefore, the FFRDc RFP was amended on June 2, 1998, to remove all requirements related to the PRIME RFP and bid evaluation.
Management’s indecision on contractor responsibilities helped delay awarding the new FFRDc contract. For instance, the RFP, issued December 27, 1996, outlined five proposed tasks. In July 1997, Procurement orally informed potential bidders of a possible change in the number of tasks. Subsequent modifications to the RFP did not eliminate any of the original five tasks, and Information Systems personnel confirmed that all five tasks remained
We believe it is in the best interest of the government to ensure each contractor is aware of it’s responsibilities in modernizing the Service’s computer systems as well as the interdependency with other contractors’ work. The Service acknowledges that care must be taken to distinguish the work of the proposed FFRDc from the work of the other IRS contractors to prevent a conflict of interest or duplication of effort. Without identifying each contractor’s role in the effort, the Service is at risk of duplicating efforts, incurring additional costs, not receiving its anticipated outcomes, and delaying the modernization efforts.
Recommendations:
Management’s Response: Information Systems management will form a task force specifically dedicated to addressing the responsibilities of all contractors involved in the modernization effort, defining the Government’s role and contract interdependencies. Once the responsibilities and interdependencies of the three contractors and the Government have been defined, they will be made available to the contractors, as well as Service personnel using the contracts.
Management’s Response: To manage the three key modernization contracts, IS will form a governing committee within the contract Management Organization for task assignment management and oversight. The main focus of the governing committee will be to ensure that overlap and redundancy of tasks assigned to multiple contracts does not occur. The governing committee will develop a set of guidelines for task assignment. These guidelines may not be published with an IRS document number, but may be issued in a memorandum. The governing committee will implement the guidelines for task assignment immediately.
Procurement officials do not have sufficient measures for ensuring a FFRDc remains free of organizational conflicts of interest. currently, the FFRDc contractor signs a statement agreeing to maintain its objectivity and independence. However, Procurement does not validate the contractor’s compliance with this statement.
The Office of Procurement Policy Letter 84-1 created government-wide policies for the establishment, use, periodic review, and elimination of the sponsorship of FFRDcs. This policy letter states the FFRDc is required to operate in the public interest free from organizational conflicts of interest, and disclose its affairs to the primary sponsor. In addition, the Federal Acquisition Regulations (FAR) 35.017-4 dictate the FFRDc’s ability to maintain its objectivity and independence be reviewed.
Procurement plans to require the new FFRDc bidders to submit their policies and procedures for maintaining freedom from organizational conflicts of interest. The selected contractor’s policy and procedures will be incorporated into the contract. However, incorporating the policies and procedures into the contract does not ensure freedom from organizational conflicts of interest.
We were advised that the existing FFRDc—IITRI almost engaged in a potential organizational conflicts of interest situation. Under a separate contract, IITRI had initiated negotiations with a contractor who is a major contributor to the Service’s modernization efforts. The Service discussed the situation with IITRI and IITRI voluntarily declined the work.
Only by chance did the Service learn of IITRI’s potential organizational conflicts of interest. The proposed contract for the new FFRDc requires the contractor to notify the contracting Officer of apparent or actual organizational conflicts of interest and submit a mitigation plan. However, Procurement does not have any measures to ensure the selected contractor complies with this requirement. Therefore, we believe a periodic validation of the FFRDc’s compliance with its internal policies and procedures should be implemented.
The need for the FFRDc contractor to be impartial is vital because during the 15-year life of the multi-billion dollar PRIME contract, the FFRDc contractor will be evaluating the PRIME’s performance and providing recommendations. If the FFRDc is not free from conflicts of interest, the Service can not rely upon the evaluations and recommendations provided by the FFRDc.
Recommendations:
Management’s Response: The FFRDc contract awarded on October 8, 1998, requires the contractor’s compliance with an organizational conflict of interest mitigation plan, incorporated into the contract, and it requires the contractor to ensure that this plan is maintained and updated throughout the life of the contract. The contract also requires the contractor to provide to the contracting officer an annual report and certification regarding compliance with the conflict of interest mitigation plan.
Management’s Response: The FFRDc contract, awarded on October 8, 1998, requires the contractor to submit to the contracting officer for review an annual report on the performance of non-Treasury tasks.
Nancy LaManna
Audit Manager
Internal Audit Team:
Regina Dougherty, Senior Auditor
Dawn Smith, Internal Auditor
Attachment I
The overall objective of this review was to determine whether the solicitation process for the new FFRDc contractor was effective. Our detailed objectives and audit tests are outlined below.
Attachment II
Management's Response has been removed due to its size. To see the complete Response, please go to the Adobe PDF version of this report.